106
Item
Check Method
Maintenance
Interval
caps.
Grounding
reliability
Check that ground cables are securely connected.
The first inspection is
half a year after the
initial commissioning.
From then on, perform
the inspection once six
months to a year.
Table 9-2
Spot check list
Item
Check Method
Spot-check
terminal signal
detection (2-pin
spot-check
terminal)
The spot-check terminal signal measures the protection time of the
AC relay.
shows the cable connection to the spot-check terminal.
describes the ports on the spot-check terminal.
Spot-check
terminal signal
detection (12-pin
spot-check
terminal)
The spot-check terminal signal measures the protection time of the
AC relay, impedance between the PV input string and the ground,
and the impedance between the SUN2000 DC input and the
ground.
shows the cable connection to the spot-check terminal.
describes the ports on the spot-check terminal.
Figure 9-1
Connecting cables to a 2-pin spot-check terminal