1. Pull out the BCU.

- +

PE

Do not open the front cover of a battery module when installing or moving 

it.

Assign at least three persons or use a lifting trolley to move a battery 

module. When using a lifting trolley to move a battery module on the 

aisle, adjust the trolley angle to facilitate installation.

Install the battery modules from bottom to top and from left to right to 

prevent falling over due to imbalance.

If half-capacity cabinet configuration is adopted, battery modules can be 

installed only on the left side. Install a filler panel at the last but one layer 

of the right column only after installing battery communications cables.

2. Install battery modules and filler panels.

3. Check the insulation performance of the battery 

modules and secure the modules. (7+7 scenario 
used as an example)

It is recommended that you use the DC voltage 
mode of a multimeter to measure the voltage 
between the ground point and the positive and 
negative terminals of each battery module 
respectively.  If the readings are less than 6 V DC, 
the insulation is good. Otherwise, contact 
technical support engineers.

Battery 
baffle plate

4. Install battery communications cables.

8+8

8+0

7+7

7+0

6+6

6+0

8+8

8+0

7+7

7+0

6+6

6+0

Excessive bolts will be used as spare parts.

When installing cables, ensure that the cables do not 
block the QR code on the left of the protective 
cover.

5. Install battery copper bars and power cables. (7+7 

scenario used as an example)

Round 

hole

Slotted 

hole

7. After checking that the battery strings are well 

insulated, close the front cover of each battery module.

6. Check the insulation between the battery 

strings and the cabinet.

It is recommended that you use the DC voltage mode 
of a multimeter to measure the voltage between the 
battery tray and the positive and negative terminals of 
each battery string respectively.  If the readings are less 
than 6 V DC, the insulation is good. Otherwise, contact 
technical support engineers.

8. Attach PP sheets to the notches of the battery 

modules on the top layer to prevent foreign 
matter from falling into the cabinet. (7+7 
scenario used as an example)

When attaching PP sheets, align them with 
the edge of the front cover of battery 
modules and ensure that the front cover can 
be opened and closed properly after PP sheets
are attached.

9. Reinstall the BCU.

10.Select the corresponding  model on the 

nameplate of the cabinet based on the number of 
installed battery modules. (The figure uses 14 
battery modules as an example.)

05

Installing Battery Modules

Do not open the protective covers for the positive 
and negative terminals of a battery module at 
the same time. Close the protective covers for the 
terminals where copper bars have been installed.

After removing the safety cap from a power 
cable, install the cable immediately  to prevent 
the exposed terminal from touching the shell, 
which may cause sparks or burns.

a. Open the protective covers for the negative terminal of 

the battery module on the upper layer and the positive 
terminal of the battery module on the lower layer.

b. Install copper bars between battery modules. Install the 

copper bar end with a round hole at the battery 
module on the upper layer, and close the terminal 
protective cover. Install the copper bar end with a 
slotted hole at the battery module on the lower layer, 
and close the terminal protective cover.

c. Repeat these two steps.
d. Open the terminal protective covers, install the battery 

power cables reserved in the cabinet, and close the 
terminal protective covers.

Summary of Contents for SmartLi-512V-162Ah-F

Page 1: ...ncluding the Insulation Layer Unit mm Recommended Cable Size Unit mm2 M40 10 32 Innermost layer white 10 16 Innermost layer white second to last layer red 16 22 70 95 120 The single core 90 C resistant flexible copper cable is used as an example in the table to illustrate which sealing plugs need to be removed The sealing plugs to be removed depend on the actual cable diameter including the insula...

Page 2: ...nd crimp the DT terminal Marked DT terminal direction Marked cable cutting position 1 Set the switch based on the actual load Installing Output Power Cables 250 kW Load of a single battery cabinet 300 kW 200 kW Load of a single battery cabinet 250 kW Load of a single battery cabinet 200 kW 2 Install power cables UPS Without a Neutral Wire UPS With a Neutral Wire Connect cables correctly to avoid b...

Page 3: ...battery strings and the cabinet It is recommended that you use the DC voltage mode of a multimeter to measure the voltage between the battery tray and the positive and negative terminals of each battery string respectively If the readings are less than 6 V DC the insulation is good Otherwise contact technical support engineers 8 Attach PP sheets to the notches of the battery modules on the top lay...

Page 4: ...easures for example using a dust cover plastic film or fabric cloth to prevent battery condensation or dust corrosion Remove the protective material when batteries need to be used The BCB off alarm the red indicator is steady on is displayed on the SmartLi LCD No action is required After the battery circuit breaker is switched on the alarm will be automatically cleared The green indicator blinks i...

Page 5: ...when the discharge current is 0 1C 0 3C 0 5C or 1 0C respectively 1 8 Dis cur 0 3C EOD V cell 1 8 Dis cur 0 5C EOD V cell 1 75 Dis cur 1 0C EOD V cell 1 75 If a third party UPS is connected and the EOD is not distinguished by rate set this parameter to 1 8 V cell If a third party UPS is connected set this parameter to the maximum value If the UPS from the Company is connected set Batt charging cap...

Page 6: ... Number of lead acid batteries supported is 252 42 x 12 2 252 in the 7 7 7 0 scenario 8 8 8 0 scenario 276 8 8 8 0 scenario 276 300 7 7 7 0 scenario 252 7 7 7 0 scenario 240 270 6 6 6 0 scenario 204 6 6 6 0 scenario 192 234 Battery cabinet quantity Specifies the number of battery cabinets connected in parallel Currently a maximum of 10 lithium battery cabinets can be connected in parallel 1 1 10 A...

Reviews: