4.
Installation engineer C pulls the lifting sling downwards, and installation engineer D pulls
the traction sling outwards to protect the fiber optic cables from colliding with the tower.
Step 2
Secure the fiber optic cables to the tower vertically using cable clips.
Step 3
Remove the lifting sling, traction sling, and protection pipe.
NOTE
The procedure for hoisting the fiber optic cables onto the tower is for your reference only.
----End
7.3 Hoisting Power Cables onto a Tower
This section describes the procedure for hoisting power cables onto a tower and the precautions
that must be taken.
Context
Cabling requirements for power cables are met. For details, see
.
The procedure for adding a connector to the RRU power cable on the RRU side is done under
the tower.
Procedure
Step 1
Hoist the power cables onto the tower, as shown in
.
RRU3268