PowerCube 5000 (SUN2000-150KTL-S0)
Installation Guide
3 Installing the Cabinet
Issue 03 (2020-04-10)
Copyright © Huawei Technologies Co., Ltd.
27
Figure 3-9
Installing the waterproof panel
----End
3.2 Installing an Isolation Transformer
Context
In this example, an 80 kVA isolation transformer is installed.
Procedure
Step 1
Unpack the isolation transformer.
Step 2
Mark the position of the cabinet based on the delivered marking-off template.
Step 3
Remove the blocking piece on the mounting hole of the isolation transformer base.
Step 4
Drill holes and install expansion sleeves.
1.
Drill a hole into the concrete floor using a hammer drill. The hole depth should range
from 52 mm to 60 mm.
2.
Slightly tighten the expansion bolt and vertically insert it into the hole. Knock the
expansion bolt using a rubber mallet until the expansion sleeve is fully inserted into the
hole.
3.
Partially tighten the expansion bolt.