3.4.3 Installing a Signal Cable
When connecting cables, ensure that dry contacts OL, STA, DRV, and 0V on the UPS dry
contact card correspond to control signal ports OL, STA, DRV, and GND on the BCB box
respectively.
If the cable length is insufficient, prepare the signal cable onsite. To ensure that the cable
sequence is correct, you are advised to attach labels to the cable. Ensure that the signal
cable is no longer than 50 m.
Single Battery String
Step 1
Connect a signal cable between the BIB and the MUE05A.
Figure 3-12
Connecting the control signal cable on the BCB box (old BIB board)
Table 3-7
Mapping relationship of ports
MUE05A BCB Signal Port BIB J1 Signal Port
Description
OL
5 OL
BCB box connected
STA
6 STA
BCB box circuit breaker
state
DRV
7 DRV
BCB box trip control
0V
8 GND