Installing Cables 

This document uses the dual-input top cable routing and single-input bottom cable routing as 
examples. Cable connections for other scenarios are similar. 

1. Ensure that all circuit breakers, including upstream output circuit breakers, are switched to OFF 

before connecting cables. 

2. The PDC ground cable is secured to the equipment room ground bar. The resistance between 

the PDC ground cable and the equipment room ground bar is less than 0.1 ohm. 

3. The N and PE cables are bound separately from the L1/L2/L3 or L cables for each circuit 

breaker. Cables are converged at the beam and bound in groups by cable ties. 

NOTICE

1. Remove the rodent-proof meshes at the top and put them aside. 

Connecting cables (Top Cable Routing) 

NOTE

Cable holes at the PDC bottom 

Cable holes on the PDC top 

Power cable inlet 

 

Cable Hole Description 

Monitoring cable hole 

Power cable outlet 

 

Power cable inlet 

 

Power cable outlet 

 

2. Remove the transparent covers of the N bar 

and input copper bar, and put the covers 
aside. 

3. Connect cabinet ground cables. 

Summary of Contents for PDC V2.0

Page 1: ...HUAWEI TECHNOLOGIES CO LTD PDU8000 Modular Precision PDC V2 0 Quick Guide Issue 03 Part Number 31508339 Date 2018 01 25 ...

Page 2: ...ng current Rated voltage level Precision power distribution cabinet SN The table describes the model of the PDU8000 series products using PDU8000 0630ACV4 SCAY52 as an example 1 Indicator of route I 2 Indicator of route II 3 Input circuit breaker of route I 4 Input circuit breaker of route II 5 SPD and SPD circuit breaker of route I 6 SPD and SPD circuit breaker of route II 7 Monitoring board 1 8 ...

Page 3: ...e buzzer is sounding at intervals of 0 5s Green A warning has been generated or the precision PDC is running properly Off The MDU is powered off Monitoring Board No Port Function 1 MUS05A N A 2 FE Network port connecting to the management system when the PDU8000 uses SNMP or Modbus TCP 3 CAN Internal communications and power supply port for the MDU LCD 4 RS485_1 Northbound serial port connecting t...

Page 4: ... this document can be performed selectively based on the actual configuration NOTICE 1 Due to the limitations of the door height you can move the device into the equipment room by tilting it Keep it upright in the equipment room 2 Take protective measures during moving the PDC to prevent toppling and bumping 3 During movement be careful to avoid squeezing the MDU screen Moving the PDC 2 1 CAUTION ...

Page 5: ... that all cabinet surfaces are at the same level NOTE 1 Open the front and rear doors Wrench the anchor bolts using an adjustable wrench to adjust the cabinet height 2 Remove the cabinet connecting kits from the rack 3 Screw the connecting kits in the connection positions on the front door 4 Use the same method to secure the connecting kit in the connection positions on the rear door 5 Repeat the ...

Page 6: ...uipment room ground bar is less than 0 1 ohm 3 The N and PE cables are bound separately from the L1 L2 L3 or L cables for each circuit breaker Cables are converged at the beam and bound in groups by cable ties NOTICE 1 Remove the rodent proof meshes at the top and put them aside Connecting cables Top Cable Routing NOTE Cable holes at the PDC bottom Cable holes on the PDC top Power cable inlet Cabl...

Page 7: ...rt on the MDU side panel 1 Monitoring cable outlet 8 Optional Connect the fire linkage cable by referring to Appendix B 9 Cut suitable holes in the rodent proof meshes and reinstall the rodent proof meshes 10 Reinstall the transparent covers of the input copper bar and N bar 11 Seal the gap between cables and the cabinet using flake sealing putty Remove the paper protective film from the sealing p...

Page 8: ...e output power cables Connecting Cables Bottom Cable Routing 1 Remove the rodent proof meshes at the bottom and put them aside 2 Remove the transparent covers of the N bar and input copper bar and put the covers aside 3 Connect cabinet ground cables ...

Page 9: ...e linkage cable by referring to Appendix B 9 Cut suitable holes in the rodent proof meshes and reinstall the rodent proof meshes 10 Reinstall the transparent covers of the input copper bar and N bar 11 Seal the gap between cables and the cabinet using flake sealing putty Remove the paper protective film from the sealing putty and use the aluminum foil film together with the sealing putty Flake sea...

Page 10: ...sary adhesive tape or cable tie on cables Yes No 5 Exposed parts of wires and cable lugs near the wiring terminals are wrapped by insulation tape or heat shrinking tubing Yes No 6 The routing of power cables and monitoring cables meets the requirements for routing signal cables and power cables and complies with the cable routing planning Yes No Cable installation checklist 4 3 4 Check Before Powe...

Page 11: ...n the input power circuit breaker to power on the PDC If the power indicator on the front panel of the PDC lights up the PDC is powered on properly If the indicator of an SPD module is green the SPD module is running properly If an indicator is red the corresponding SPD module has failed and must be promptly replaced The input power circuit breaker refers to the output circuit breaker that control...

Page 12: ...figures are for reference only The actual parameter values prevail NOTE 6 After the quick settings are complete if the monitoring page displays alarms clear the alarms 7 Turn on the PDC input switches 8 Switch on the output circuit breakers except reserved circuit breakers in the PDC in sequence to power on the corresponding devices and check whether the monitoring parameters on the MDU screen are...

Page 13: ...Power input PE 160 25 DT M10 27 250 50 DT M10 27 400 95 DT M12 47 630 2 x 95 DT M12 47 AC output L 10 2 5 Cord end terminal crimping screw specification M4 1 2 10 I 40 6 Cord end terminal crimping screw specification M4 1 2 40 I 63 10 Cord end terminal crimping screw specification M4 1 2 AC output N PE 10 2 5 OT M6 4 5 10 I 40 6 OT M6 4 5 40 I 63 10 OT M6 4 5 For the installation torque for power ...

Page 14: ...negative terminals of each pair of control cable to the 24VDC and 24VDC wiring terminals at the rear left and rear right of the cabinet respectively NOTE 1 24 V DC cables routed into the PDC should be shielded cables 2 Ensure that the polarities of 24 V DC cables routed into the PDC are correct Single input PDC Connect the positive and negative terminals of the fire control cable to the 24VDC and ...

Page 15: ...port huawei com Support Support E WeChat Google Play Scan here for technical support enterprise Scan here for technical support carrier Google Play Huawei App Store Huawei App Store Huawei Technologies Co Ltd Huawei Industrial Base Bantian Longgang Shenzhen 518129 People s Republic of China www huawei com Apple Store Apple Store ...

Reviews: