background image

 

 

 

 

 

 

 

 

 

 

ILRB-3000 GEA20261

 RAS and RAS-J WHISPAIR Blowers

 

Page 9 of 33 

 

when using these materials. Care must be exercised when 

employing non-shrink additives with cement, as too much 

can be worse than none. Any gas-forming or air-entraining 
additives should be avoided, because they tend to reduce 
grout strength. 

Wait at least 24 hours before tightening anchor bolts or 
connecting piping. When jack screws have been used for 
levelling, make sure the bottom of the levelling screw is 
treated according to the grout manufacturer’s instructions 
so that it can be backed off. Such points of concentrated 
loading are likely to wear during machine operation, 
resulting in loose anchor bolts. Final bolt tightening should 
only be enough to hold the machine firmly against the 
foundation and prevent vibration. 

After all anchor bolts are secured, recheck the blower for 
twist and level. Working from the finished pad on top of the 
cylinder, make corrections to meet the requirements 
specified under LEVELING by shimming under the blower 
feet. Then rotate the drive shaft by hand to make sure both 
impellers turn freely at all positions. 

When the blower is directly coupled to its driver, final 
alignment of the two shafts should be accomplished by 
very carefully adjusting the shims under the driver feet. 
While a flexible coupling can accept some degree of 
misalignment, it should not be forced to compensate for 
careless workmanship. The flexing or sliding member in a 
coupling transmits undesirable forces between the two 
shafts in proportion to the degree of misalignment, thus 
promoting vibration and unnecessary wear problems. 

The two basic types of misalignment − offset and angular − 
often occur together. Use the following limits to achieve 
satisfactory coupling operation: maximum deviation in 
offset alignment not greater than .005 inches (.13 mm) total 
indicator reading on the coupling hubs, and maximum 
deviation from parallel of the inside coupling faces not 
greater than .001 inches (.03 mm) when checked at six 
points. When the driver is a steam turbine, the final 
alignment should be made with the turbine at operating 
temperature in order to allow for shaft movement resulting 
from expansion. 

Piping 

Before connecting the piping, thoroughly clean it. The 
piping should be sized so that air velocity in the line does 
not exceed 100 feet per second (30 m per second). When 
a blower is operated at or near its maximum volume rating, 
the piping should be no smaller than the blower 
connections. 

Use long radius elbows whenever possible to ensure 
smooth flow. Design the piping layout so that no strain is 
placed on the blower, either from weight or expansion 
forces. Provide adequate supports, anchors, and  
expansion joints or loops. 

We recommend installing a spool-type rubber expansion 
joint near the blower inlet connection. In addition, a similar 
unit with control elements added to minimize piping 
vibrations may be required near the discharge. Depending 
on the blower speed, operating pressure, length and type 
of piping, and surrounding area sound level requirements, 
the use of snubbers or silencers in  

 

the inlet or discharge piping may be necessary. For specific 
silencer recommendations, contact your nearest Howden 
Roots sales office. 

Typically, inlet piping should be free of valves or 
restrictions, but when a shutoff valve cannot be avoided, 
make sure a full-size vacuum relief valve is installed near 
the blower inlet connection (see Figure 5). This will protect 
against an overload caused by accidental valve closing. 
Further protection can be provided by installing a 
dependable pressure-sensitive device with an alarm or 
shutdown action. 
During initial operation, install a temporary corrosion-
resistant screen at the compressor inlet connection. The 
screen should be made of 16 mesh (.020 inch diameter) 
wire backed with 2 mesh wire cloth. The backing cloth-wire 
diameter should be a minimum of: 

• 0.063 inch diameter for 12-inch pipe 

• 0.080 inch diameter for 16-inch pipe 

ILRB-3000 GEA20261 RAS and RAS-J WHISPAIR Blowers.pdf   9

03/09/2015   13:21:26

Summary of Contents for Roots RAS Whispair

Page 1: ...www howden com Roots RAS and RAS J Whispair Blower 10 20 Splash Lubricated Installation Operation Maintenance Manual ...

Page 2: ...quate safeguards against accidents to persons working on or near the equipment during both installation and operation See SAFETY PRECAUTIONS Install all equipment correctly Foundation design just be adequate and piping carefully done Use recommended accessories for operating protection Make sure both driving and driven equipment is correctly lubricated before start up See LUBRICATION In event of t...

Page 3: ... of reasonable inlet or discharge pressure variations To change the capacity it is necessary to change the speed of rotation or vent some of the air The Roots RAS WHISPAIR Operation of the proprietary Roots RAS WHISPAIR blower is represented in Figure 2 Just as in the standard Roots RAS blower the air flow is from right to left with the lower shaft rotating clockwise This design differs from the b...

Page 4: ... temperature rises higher than those listed in applicable Table 1 However you must request specific approval from the nearest Howden Roots office before doing so otherwise the warranty will be voided Normally when a blower is operated at the design conditions stamped on its nameplate the specified limits apply Pressure The pressure rise between blower inlet and discharge must not exceed the figure...

Page 5: ...ILRB 3000 GEA20261 RAS and RAS J WHISPAIR Blowers Page 5 of 33 ...

Page 6: ...ation of the connected system Nox Rust VCI 10 may be obtained from Daubert Chemical Co 2000 Spring Rd Oak Brook IL 60521 2 Paint the shaft extension inlet and discharge flanges and all other exposed surfaces with Nox Rust X 110 or equivalent 3 Seal the inlet discharge and vent openings It is not recommended that the unit be set in place piped to the system and allowed to remain idle for extended p...

Page 7: ...tion All piping requires flexible sections and supports to reduce connection strains on the unit We also do not recommend the direct use of structural framing members for mounting the blower base to a building structure If this is unavoidable it should be restricted to smaller frame size units and spring type mountings should not be used Structural members must be rigid and will probably require r...

Page 8: ...ctly under the driver feet before setting the unit in place to achieve more accurate final alignment Establish spacing between the two shaft ends as required by the coupling If a motor is being used that has end play in the shaft be sure its rotor is located on magnetic center before setting this spacing It also needs a limited end fl oat kit When the blower is driven through V belts the driver mu...

Page 9: ...bs and maximum deviation from parallel of the inside coupling faces not greater than 001 inches 03 mm when checked at six points When the driver is a steam turbine the final alignment should be made with the turbine at operating temperature in order to allow for shaft movement resulting from expansion Piping Before connecting the piping thoroughly clean it The piping should be sized so that air ve...

Page 10: ... unloading valve permits starting under no load conditions The optional back pressure regulator shown in Figure 5 is required if volume demands vary while the blower operates at a constant speed It may be vented if only air is being handled Depending on permissible sound levels in the general surroundings a vent silencer may be required In some installations particularly when two or more blowers d...

Page 11: ...in the gearbox itself through a metering orifice in the secondary wall The lower gear teeth pick up oil and carry it to the meshing point with the upper gear where it is splashed onto oil control shields with leaders that direct the oil to the two bearings A dam at each bearing maintains the desired oil level there with excess overflowing into the gearbox primary sump Inboard sealing of the shafts...

Page 12: ...he sight glass a satisfactory amount of oil is present During the fi rst week of blower operation check the oil level daily and watch for leaks Replenish oil as necessary Thereafter an occasional check should be sufficient Drain plugs 67 and 88 are provided at the bottom of the gearbox and bearing sumps Common Opposite Gear End Reservoirs Some blowers are equipped with a common reservoir on the op...

Page 13: ...blower is ready for trial operation under no load conditions The following procedure is suggested for this initial operation test period 9 Start the blower let it accelerate to full speed and then shut it off Listen for any knocking sounds both with the power on and also as it slows down 10 If no problems have been noted after the blower comes to a complete stop restart the unit and let it operate...

Page 14: ...strict the vents Do not use air blowers on explosive or hazardous gases Other potential hazards to safety may be associated with operating this equipment All personnel working in or passing through the area should be warned by signs and trained to exercise adequate general safety precautions Preventive Maintenance Daily Record the following Lube oil pressure if applicable Lube oil temperature if a...

Page 15: ...repack with fresh grease Inspect oil cooler tubes as applicable Check all protective switches for proper set points and operation Check v belt drive condition and tension Note A preventative maintenance schedule should be established for drivers and all accessories in accordance with the applicable manufacturer s recommendation ...

Page 16: ...ILRB 3000 GEA20261 RAS and RAS J WHISPAIR Blowers Page 16 of 33 ...

Page 17: ...epends on the number of impeller tips contacting the cylinder and can range from one to four times the RPM Impeller to head plate contact The vibration frequency is erratic and unsteady Damaged gears generate vibrations at mesh frequency number of teeth times RPM Damaged bearings generate vibrations at ball pass frequency fundamental train frequency and ball spin frequency Rotor unbalance and a be...

Page 18: ...rings Experience indicates that a high percentage of bearing failure is caused by dirt contamination before or during assembly Therefore clean the work area before starting disassembly and protect new or reusable parts as work progresses The following detailed work procedures describe repairs and adjustments that can typically be handled successfully at the installation site While reading the inst...

Page 19: ...f a turn at a time Check that the screws cannot be turned any more by applying the specified torque Removing 10 Taper Bore Gears 1 Remove the gear nut 2 Install Gear Remover within 1 8 inch of the gear face Note This gap is necessary to unseat the gear from the shaft taper 3 Apply Neverseez on 3 4 10X3 long grade 8 cap screw threads and under the hex heads 4 Install cap screws through the gear rem...

Page 20: ...e installation cap screws Finger tighten the cap screws 6 Install the indicator on the gear outside face for measuring the gear axial movement 7 Tighten each screw a quarter turn at a time in either a clockwise or counter clockwise sequence not a diametrically opposite sequence until the outer ring is solid against the inside ring Note The gear should move 065 to 075 inches 8 Loosen up the install...

Page 21: ...king sure that any gear tooth clearance is always taken up in the same direction Note There are two front and two back clearance positions in one complete revolution Use the minimum clearance value found along the length of impeller for fronts and backs throughout a 90 degree rotation 4 Loosen the screws on one gear make sure the collars are loose to permit slight adjustments of position relative ...

Page 22: ...oard seal replacement Reversible CW CCW green coated seal for drive shaft seal replacement Protective sleeve tool inboard seals Protective sleeve tool drive shaft seal Warning For seals to perform properly Use careful handling procedures to avoid damaging the seals during installation Use the installation sleeves provided in the kit as described in Operation F below Seal lips are not very flexible...

Page 23: ...ILRB 3000 GEA20261 RAS and RAS J WHISPAIR Blowers Page 23 of 33 ...

Page 24: ...earances and forces the bearing rollers and races to center as in normal running Refer to Figure 15 6 Set the impellers lengthwise in the case using long pieces of shim stock or feelers as wedges between the two ends of each impeller and the headplates Apply the total end clearance obtained in Step 8 of Operation D to the two ends of each impeller and the headplates Place wedges equal to two third...

Page 25: ...ILRB 3000 GEA20261 RAS and RAS J WHISPAIR Blowers Page 25 of 33 ...

Page 26: ...condition this information is not essential in field service work However if a situation occurs in which it would be helpful to compare existing clearance to original values Table 8 or 9 lists the ranges of values used in original factory assembly Clearances may change in service but they should never be less than the minimum values listed Only well qualified personnel should attempt to measure cl...

Page 27: ...ILRB 3000 GEA20261 RAS and RAS J WHISPAIR Blowers Page 27 of 33 ...

Page 28: ...ILRB 3000 GEA20261 RAS and RAS J WHISPAIR Blowers Page 28 of 33 ...

Page 29: ...ILRB 3000 GEA20261 RAS and RAS J WHISPAIR Blowers Page 29 of 33 ...

Page 30: ...ILRB 3000 GEA20261 RAS and RAS J WHISPAIR Blowers Page 30 of 33 ...

Page 31: ...ILRB 3000 GEA20261 RAS and RAS J WHISPAIR Blowers Page 31 of 33 ...

Page 32: ...ILRB 3000 GEA20261 RAS and RAS J WHISPAIR Blowers Page 32 of 33 ...

Page 33: ...operations Howden people live to improve our products and services and for over 150 years our world has revolved around our customers This dedication means our air and gas handling equipment adds maximum value to your operations We have innovation in our hearts and every day we focus on providing you with the best solutions for your vital operations ...

Reviews: