4.4
Electrical connection
The electrical connection must be established by a li-
censed and qualified electrician.
For Austria and Germany:
An electrical circuit diagram is supplied with the boiler
controls. An all-phase main switch with a minimum con-
tact spacing of 3 mm must be fitted in the power supply
line.
For Switzerland the following applies:
For the electrical connection, the circuit diagram specific
to the plant must be observed.
Do not reach into the marked area (Fig.
37) when folding out the switch control
box.
Danger of cuts and pinching in the area of
the trim strip (A).
Wear gloves. Grip the switch control box
by the left and right sides, not by the un-
derside!
1. Schalldämmhaube (1, Fig. 23) abnehmen, dazu
seitliche Sicherungsbolzen (2) lösen (ca. ¼- Drehung
links und bis Anschlag herausziehen).
2. Untere Frontabdeckung (3) abnehmen, dazu seitliche
Sicherungsbolzen (4) lösen (ca. ¼- Drehung links
und bis Anschlag herausziehen).
3. Sicherungsschraube (5) entfernen, dazu Abdeck-
blech-Klemmleiste nach oben anheben (6) und weg-
nehmen.
4. Sicherungsschraube (7) entfernen und Elektrokasten
herausklappen.
5. Kabeleinführung (9).
Der Elektroanschluss soll anhand des beigelegten Sche-
mas e
rfolgen.
1
2
3
5
4
7
8
9
6
A
A
Fig. 37
22
4 210 255 / 02
INSTALLATION