![horsch Taro 6 HD Operating Instructions Manual Download Page 23](http://html1.mh-extra.com/html/horsch/taro-6-hd/taro-6-hd_operating-instructions-manual_2164122023.webp)
60029922 • 1 • 09/2020 • en
23
3 Commissioning
NOTE
These work activities may be carried out only by persons trained by HORSCH for this
purpose.
WARNING
Increased danger of accidents during commissioning.
Ø
Observe the notes in the Safety chapter and familiarise yourself with the ma-
chine!
3.1 Delivery
The machine with implements is normally delivered completely assembled on a low
loader.
If parts or assembly groups had to be disassembled for transport purposes, these
will be assembled locally by the sales partner or field technician.
Depending on the design of the low loader the machine can be unloaded with a
tractor or needs to be lifted off with suitable lifting gear (forklift truck or crane).
Ø
Use only lifting equipment and lifting gear with adequate lifting capacity and
approval!
Ø
Points with the associated stickers "Strapping point" must
not
be used for
load suspension!
When using other lifting points pay careful attention to the centre of gravity and the
weight distribution. These points must, in any case, only be on the frame of the ma-
chine.
Lift/lower
function
On all machines with drill controls the hydraulic "
Lift/Lower
" function is possible
without additional installation. These machines can be unloaded without having to
install the
ISOBUS
basic equipment.
The other hydraulic functions (such as
Folding
or
Bout marker
) can only be used
after the
ISOBUS
basic equipment has been installed on the tractor.