Figure 6 – Example Ladder Code – Trend Data and Print Job Status Fields

 

 
 

Operation Including Print Trend Report   

 

Note:   The following procedures reference the above example, which uses data in Table 1 and 

Table 2 and Ladder Code Figures 3 – 6.  

 
1.  Apply the quantities to be measured from %AI1 through %AI4.   

(This references 

Pressure, Flow Rate, Temperature and Level

 quantities.)  

 
2.  Set %M1 through %M4 to zero.    

(This references interface controls 

Print Trend, Cancel Print, Store Data, Clear Data.

 
3. Set %M5 as desired for the 

sample rate

.    

(This references the 

Scale Range

which indicates the 

time

 interval that each sample occurs.)

 

 

 
4.  Enter the 

customer name, job number, and purchase order

 information including 

their respective 

lengths

 in %R1 through %R60.    

 
5.  Set %M3 (

Store Data

) to 1 to enable 

data capture

.  Allow the network application to run until the 

desired number of sample intervals has passed.    

 
6.  Clear %M3 to zero to 

stop

 

data acquisition

.   

 
7.  Set %M1 to 

print

 the 

trend

 report.  

(Set at least one second.)

  

 

 
8.  Clear %M1 to zero.   
 

Summary of Contents for HE800PCU100

Page 1: ...face using pre programmed controls Connects to any Hewlett Packard printer with IEEE 1284 parallel port and that uses PCL3 such as HP Deskjet 5650 Provides customized reports such as alarm or industry specific reports available for additional cost by contacting Horner Sales staff An example of a data trend report is on the last page of this document 2 Configuration Overview 2 1 Brief Summary of St...

Page 2: ...nd that uses PCL3 or greater Note Our example uses one PCU but multiple PCUs can be connected to the CsCAN network Figure 1 PCU Setup in a CsCAN Network 2 3 Interface Configuration Software Cscape software is used to interface the PCU to the OCS over a CsCAN network 2 4 Ladder Programming You need to build a ladder program subroutine or sequence that uses NETPUT and NETGET to configure and control...

Page 3: ...ter OCS The default screen appears b At the top of the menu bar click on the Program tab c Select Network Config from the pull down menu d Click the Option tab The following Network Configuration screen appears Figure 2 Network Configuration Screen e Click the Network Required box to the other network options f Click the Network Optimized box to speed network transfers g Fill in the Number of Netw...

Page 4: ...CLEAR DATA Momentary QG5 1 M5 SCALE RANGE Time Toggle On state 0 25 minutes samples every 3 seconds Off state 0 25 hours samples every 30 seconds AQG1 1 R1 Customer name field length Number of charters in customer field AQG2 1 R2 Customer name field 30 ASCII Characters max 15 registers AQG1 2 R21 Job number field length Number of characters in job number field AQG2 2 R22 Job number field 30 ASCII ...

Page 5: ...through the code and relate it back to the register assignments in the Tables 1 and 2 Note For all ladder code examples the Master OCS uses ID 1 through 4 The PCU uses default ID 10 You need to build a ladder program subroutine or sequence that uses NETPUT and NETGET to configure and control the PCU Examples of ladder code programs are shown in Figures 3 6 Figure 3 Example Ladder Code HeartBeat ...

Page 6: ...PAGE 6 19 APR 2005 MAN0790 01 Figure 4 Example Ladder Code Command Controls and Customer Name Fields Figure 5 Example Ladder Code Job Number and Purchase Order Fields ...

Page 7: ...h M4 to zero This references interface controls Print Trend Cancel Print Store Data Clear Data 3 Set M5 as desired for the sample rate This references the Scale Range which indicates the time interval that each sample occurs 4 Enter the customer name job number and purchase order information including their respective lengths in R1 through R60 5 Set M3 Store Data to 1 to enable data capture Allow ...

Page 8: ... personal protective equipment including safety glasses and insulated gloves when making connections to power circuits Ensure hands shoes and floor are dry before making any connection to a power line Make sure the unit is turned OFF before making connection to terminals Make sure all circuits are de energized before making connections Before each use inspect all cables for breaks or cracks in the...

Page 9: ...e OCS OCX e g OCS1XX 2XX Graphic OCS250 Remote Control Station Hardware RCS except RCS116 RCX e g RCS210 RCS250 MAN0227 Color Touch OCS Hardware e g OCS300 OCS301 OCS350 OCS351 e g OCS451 OCS551 OCS651 MAN0465 OCS LX Series Hardware e g LX280 LX300 RCS116 MAN0755 MiniOCS MiniRCS MiniOCX MiniRCX Hardware e g HE500OCSxxx MAN0305 Other Useful References Cscape Programming and Reference MAN0313 Device...

Page 10: ...PAGE 10 19 APR 2005 MAN0790 01 NOTES ...

Reviews: