LMAN0009-03-EN
ETG-LRP INSTALL SHEET
6/20/2014
No part of this publication may be reproduced without the prior agreement and written permission of Horner Lighting Group, LLC. Information in this document is subject to change without notice.
Page
2
of
5
2. GETTING STARTED
2.1 Shipping Weight
ETG-LRP1060
– 1 Tube – 3.53 lbs. | ETG-LRP2160 – 2 Tube – 7.30 lbs.
ETG-LRP3240
– 3 Tube – 10.9 lbs. | ETG-LRP4320 – 4 Tube – 14.6 lbs.
ETG-LRP6480
– 6 tube – 21.8 lbs.
2.2 Unboxing
Our packaging is designed to protect the luminaire during shipping. Please inspect to confirm it was
not damaged in during the process.
2.3 Handling
Once unpacked, the luminaire can become damaged if mishandled. Do not stack luminaires after
unpacking. Protect the remote phosphor plate from scratching.
2.4 Package Contents
-
Light fixture - LED tubes, power supply, heat sinks (assembled)
-
Installation Instructions
-
Reflector
-
Reflector Lock Clips
2.5 Recommended Accessory (Mounting)
-
ETG-YSM-05: Y-mounting cables with hook ends.
-
Pendant Mount System
3. INSTALLATION
It is recommended to first mount the LRP fixture in the desired position before installing reflectors. The
LRP series come packaged with the selected reflector as ordered to suit a variety of applications.
3.1 Mounting
The LRP can be mounted using a variety of hardware, such as cable, hook, or chain. The following
steps utilize the recommended ETG-YSM-05 Mounting Cables:
1) Install cable to the desired fixture height using proper hardware based on application (follow local
code if necessary).
2) Loop cable around mounting point or hardware and slide through locking mechanism.
3) Locate Mounting Holes in bracket (shown in Figure 1).
4) Loop hooks from mounted cable through set of holes on each end of the fixture
– 4 hooks total.
Note:
3, 4, and 6 tube fixtures will have multiple sets of holes to be used for adjustment
depending on installed height. Make sure to use set closest to center or closest to edge of
bracket for level alignment.
5) Using a leveling tool, adjust the cable length at the Locking Mechanism to level the fixture
horizontally.
Figure 1 - ETG-LRP Mounting Bracket