Creating a zoning plan
6
For more than 8 temperature zones or 24 actuators:
►
Determine the number of additional storey controllers required using
the following table:
Temperature
zones (maximum)
Actuators
(maximum)
No. of
storey controllers
8
24
1
16
48
2
24
72
3
The example at the end of this section shows zone divisions
with corresponding zoning plan.
Filling out zoning plan
►
Copy the sample zoning plan (see Appendix, Page 50) (archive it).
►
Enter the type and installation location of the respective actuator in
each temperature zone.
►
Assign a setpoint adjuster to each temperature zone.
►
Assign room names if necessary.
►
Hand over the zoning plan to the customer after installation.