d. Connect the three AC main power wires (Phases A, B and C) to their respec-
tive positions as labeled on terminal block TB1 and tighten to 7 in-lb. After all
conductors are connected to each of their respective terminal block positions
and tightened down, verify that each terminal block screw is securely fas-
tened by gently tugging on each conductor. Single phase - connect two ac
main power wires phases a and b - jumper from b to c - factory installed for
single phase option.
Verify that no conductor wires are frayed or shorting to adjacent terminal
block positions.
e. Turn ON the AC main power input. The meter display will light up and scroll
through 9 displays. Each display is visible for 5 seconds. Display screens are
as follows:
Screen 1:Total Kilowatt-Hours
(kWh)
Delivered
Received
NET
Screen 2: KWH
Screen 3: CO2
Screen 4: Peak Demand (kW) with Date & Time Stamp
Screen 5: Actual Load (kW) with present time
Screen 6: Average Current (amps) Per Phase
Screen 7: Average Voltage (volts) Per Phase
Screen 8: Average Voltage (volts) Phase to Phase