User Manual
Version 1.0 33
•
System Evacuation: the Vacuum value
•
Set Vacuum: Set the level of the vacuum pressure (P1) required to start of heating
during drying. If current vacuum > alarm P1, stop the heater.
•
Primary Drying: Set Temp (
℃
), Ramp Time(min) and Soak Time(min): Sets the process
temperatures and time as required. There are 12 possible phases available for process
control. The required time and temperature of each phase is controllable. The process
may be considered finished based on Set Temp (
℃
), or Ramp Time (min), or Soak Time
(min).
•
Pressure Rise Test: This option is available to the end of primary drying.
•
Set Pressure(mbar): Set up the maximum pressure rise P (mbar).
•
Test Time(min): Duration (min) for maximum pressure rise.
•
Test Times: Repeat set test times if the pressure rise test has failed.
•
Interval Time(min): The interval time between each test if the previous pressure rise test
has failed.
Note:
The process proceeds to the next process phase automatically if the first pressure test is
successful. If the first pressure test fails, the test should be repeated after drying is
completed for a predefined time. If several tests fail, the operator needs to manually
select continue run or abort the process.
•
Secondary Drying: Set Temp (
℃
), Ramp Time(min) and Soak Time(min): Sets the
process temperatures and time as required. There are 12 possible phases available for
process control. The required time and temperature of each phase is controllable. The
process may be considered finished based on Set Temp (
℃
), or Ramp Time (min), or
Soak Time (min).
•
Pressure Rise Test2: This option is available to the end of secondary drying.
•
Set Pressure(mbar): Set up the maximum pressure rise P (mbar).
•
Test Time(min): Duration (min) for maximum pressure rise.
•
Test Times: Repeat set test times if the pressure rise test has failed.
•
Interval Time(min): The interval time between each test if the previous pressure rise test
has failed.
Note:
The process proceeds to the next process phase automatically if the first pressure test is
successful. If the first pressure test fails, the test should be repeated after drying is
completed for a predefined time. If several tests fail, the operator needs to manually
select continue run or abort the process.
•
Stoppering: An option for stoppering in a certain vacuum, it will be performed if it is
selected.