15.1 Installation and Set-Up
HOFFMANN PP2-NCF must be installed
plumb and level in all directions.
The load capacity of the floor must be at least
2 t/m². One machine leg has a leveling bolt
and must be adjusted to have full contact with
the floor.
Check floor leveler and adjust if necessary.
Using
a machinist’s level, the machine must set plumb
and level in all directions.
Make all electrical and pneumatic connections per the
enclosed circuit diagrams and according to all local and
state laws.
Pallet truck may be used from front or rear of machine.
See section „Electrical and compressed air connections“