OM-2244 / Operation and Maintenance Manual
DCS-600/ Series 500082/ Solid State Transformer-Rectifiers
December 15, 2014
Chapter 1-2
Page 5
(1) Make sure electrical service is off.
(2) Connect the input power cables to the input power source.
(3) Connect the grounding conductor to a proper ground.
(4) Leave the electrical service turned off.
e) Connect the Output Cable
Wheel-mounted GPUs are generally shipped with the output cable already installed. For bridge-
mount or stationary GPUs, the customer must supply and connect the output cable. To connect the
output cable, follow these steps:
(1) Route the cable through the side panel and under the cable clamp.
(2) Connect the positive output lead to the positive output terminal of Output Contactor K2.
(3) Connect the negative output lead to Ammeter Shunt R11.
(4) Tighten the cable clamp.
Figure 4 Output Connections
f)
Check GPU No-Load Operation
A no-load check should be made before the GPU is connected to an aircraft. Proceed as follows.
(1) Replace the top panel.
(2) Apply input power to the GPU from the input power source.
(3) On the front panel of the GPU, turn on the input power switch.
(4) Verify that the amber input power light turns on.
(5)
Hold the output contactor switch up in the “Close” position until the green output contactor light
turns on.
(6)
Release the output contactor switch to the middle “On” position.
(7) Verify that the voltmeter shows the proper voltage.
Summary of Contents for GPU-600 Series
Page 2: ......
Page 93: ......
Page 94: ......
Page 95: ......
Page 96: ......
Page 97: ......
Page 98: ......
Page 99: ......
Page 100: ......
Page 101: ......
Page 102: ......
Page 103: ......
Page 104: ......
Page 105: ......
Page 106: ......
Page 107: ......
Page 108: ......
Page 109: ......
Page 110: ......
Page 111: ......
Page 112: ......
Page 113: ......
Page 114: ......
Page 115: ......
Page 116: ......