HEP025RT
Installation, Operation, and Maintenance Manual
L6HEP025RT
Step 3
Screw two of the supplied mounting
screws into the wall studs (or backing
plywood) at 2" and 7¾" below the
desired height, leaving ¼" of the
screw out of the wall.
Step 4
Lift panel onto mounting screws.
Step 5
Screw remaining mounting screws
into the holes at the bottom of the
panel. Tighten the top two screws.
Step 6
Refer to piping hookup and fill and
purge.
Step 7
See page 14 for optional flow switch
installation instructions.
Prior to mounting the panel, ensure the wall is capable of supporting the weight of the panel. Ensure that a 120V
receptacle is within reach of the 6-foot cord and plug and 24V plug-in transformer.
The top of the panel should be a minimum of 4 feet from the floor.
Step 1
Find and mark the wall stud locations. If the panel cannot be secured directly to the studs, or
suitable backing boards, plywood may need to be installed behind the panel to properly secure
it in place.
Step 2
Using a level, draw a line between the studs at a minimum of 4’ from the floor.
Floor
2"
7¾"
≥4'
Panel Mounting