background image

HEATIZON.COM

14

7. Installation

Concrete Preparation:

 Loose heating cable not in a mat may be secured in place by landscape 

stakes and plastic wire ties, welded wire fabric and plastic wire ties or tape, or pre-punched 

steel straps purchased from your Heatizon Distributor or Representative. Do not compress 

or strain the cable, run heavy machinery, equipment, or vehicles over it. Be careful to avoid 

stepping on the cold section factory connection of the cable. Consult the NEC or CEC for grounding 

requirements of rebar or welded wire fabric for concrete installations. When working with concrete or 

asphalt joints, design the layout so each section of the slab is covered and the cable crossing of joints 

are minimized. See page 15 for example layouts. Mats should be installed in evenly spaced runs per 

the system design and plan. Sleeve hand rail posts to avoid drilling or penetrations in the slab after the 

pour.

•  Two Pour Concrete: 

In this installation a concrete slab is already present and an additional slab will 

be poured on top.  The heating cable can be layed out using welded wire fabric and zip ties or tape, 

or pre punched steel strapping for loose cable installations not in a mat form.  Cold leads should 

be sleeved for this installation following conductor 

fill and size requirements in the NEC and CEC. The 

heating cable portion and cold connection can 

not pass into the conduit sleeve. Jumpers must be 

used to protect the heating cable where joints are 

present on the concrete slab below as well as in the 

new slab.

•  Single Pour Concrete: 

In this installation the 

aggregate or concrete base is prepared first.  Once 

the base is prepared the installer can begin by 

placing a grid of welded wire fabric or rebar in 

preparation for the heating cable. The heating 

cables or mats can be attached to the welded 

wire fabric with plastic zip ties or tape. Take note 

of layout examples on page 15 for installations 

requiring jumpers. Jumpers must be used for any 

and all joint cable crossings. Do not cross expansion 

joints.  Once the heating cable is installed, place 

chairs or concrete dobies under the rebar or welded 

wire fabric grid to bring the heating cable within 

2” to 3” of the surface. Cold leads can be sleeved 

following conductor and fill size requirements in the 

NEC and CEC. The heating cable portion and cold 

connection can not pass into any conduit sleeve.

Asphalt Preparation:

 Loose heating cable not in mat form may be secured in place by landscape 

stakes and plastic wire ties, welded wire fabric and plastic wire ties or tape, or pre-punched steel straps 

purchased from your Heatizon Distributor or Representative. Cables in a mat can be layed out in the 

configuration desired directly on the surface. Do not compress or strain the cable, run heavy machinery, 

equipment, or vehicles over it. Be careful to avoid stepping on the cold section factory connection of 

the cable. Consult the NEC or CEC for grounding requirements of rebar or welded wire fabric for asphalt 

installations. When working with concrete or asphalt joints, design the layout so each section of the slab 

is covered and the cable crossing of joints are minimized. See page 15 for example layouts. Cables or 

mats should be installed in evenly spaced runs per the system design and plan. Sleeve hand rail posts 

to avoid drilling or penetrations in the slab after the pour. 

Summary of Contents for SnoWmeltz

Page 1: ...HEATIZON COM Installation Operating Manual Warranty Registration RADIANT HEATING SYSTEMS SNOW MELTING FLOOR WARMING SPACE HEATING ROOF DEICING GUTTER DEICING 08 2020...

Page 2: ...cementitious material that goes over it Never cross the SnowMeltz Heating Cable over itself or any other conductor or wire When installing Heatizon Systems products strict compliance with the Nationa...

Page 3: ...PLAN THE DESIGN 9 3 4 JUMPERS 11 4 PRODUCT SELECTION 12 5 REQUIRED TESTS FIRST 13 6 AREA PREPARATION 13 7 INSTALLATION 14 CONCRETE 14 ASPHALT 14 SAND BED PAVERS 15 MORTAR BED PAVERS 15 STAIRS 16 8 RE...

Page 4: ...In order to have proper drainage and to reduce the likelihood of vertical shifting of your asphalt concrete or pavers Heatizon Systems recommends that a minimum of 6 inches of high quality aggregate b...

Page 5: ...is damaged it must be replaced or repaired To repair or to splice any part of the system use only Heatizon SnowMeltz Repair Kit part number SMRPKIT 1 General Guidelines 1 1 Use of the Manual This man...

Page 6: ...remely dangerous and can result in a fire Do not cut the heating cable to avoid an obstacle use other methods as described in this manual Make sure to avoid damaging cutting the heating cable during a...

Page 7: ...al Connections MATS Cable Construction Twin Conductor Rated Voltage 120VAC to 600VAC Output 12 watts ft max Length Refer to Individual Product Labels Cable Diameter 0 24 to 0 35 Cable Type Constant Wa...

Page 8: ...lt protection device i e GFCI GFEP etc requirements when installing all heating cable products Do not bend heating cable within 3 of a termination or connection between the heating element and the col...

Page 9: ...be run to the area and or met to the cold lead s Geographic Location Depending on the geographic location of the installation area some adjustments made have to be made during the installation such as...

Page 10: ...entitious material Do not bend the heating cable within 3 of cold connection Activation Devices are the eyes and ears of the heating system Location is important Please reference installation and oper...

Page 11: ...MPERS Control Joints Control Joints are intended to control where the slab will crack and are placed either in fresh concrete or saw cut in after the concrete is poured Spacing of these joints will va...

Page 12: ...34 3 12 6 10 9 60 30 20 14 SM 50W240 37W208 75 3660 30 0 15 3 13 2 75 37 20 10 SM 50W240 37W208 110 5500 9 1 22 9 19 9 110 55 20 10 SnowMeltz Mat Models 50 Watts Ft2 277VAC or 37 Watts Ft2 240VAC Heat...

Page 13: ...installed in a location that will allow it to turn the snow melt system on when it is needed and off when it is not needed Verify the proper location has been selected for the activation device Manual...

Page 14: ...aggregate or concrete base is prepared first Once the base is prepared the installer can begin by placing a grid of welded wire fabric or rebar in preparation for the heating cable The heating cables...

Page 15: ...r and fill size requirements in the NEC and CEC The heating cable portion and connection can not pass into any conduit sleeve Sand Bed Paver Preparation The heating cable may be secured in place by la...

Page 16: ...d Lead s The cold lead s should be run in a conduit to either a junction box panel or activator and should NEVER cross or come in contact with the SnowMeltz heating element 8 Required Tests Second Ins...

Page 17: ...EMOTE IN GROUND The activators usually have a head unit located indoors and have more functionality and have optional in ground sensors that detect moisture temperature on on the concrete asphalt Thes...

Page 18: ...damage by tools or paving equipment and will protect the cable from heat during placement of the main pour Continuously check the insulation resistance of the heating cables to verify that the cables...

Page 19: ...econd Insulation Resistance with Megohmmeter Before during and after installation it is necessary to measure the insulation resistance between the heating conductor and the protective grounding screen...

Page 20: ...he activator should be done AFTER completion of installing the SnowMeltz system and the substrate is fully cured completed M432 ETO2 With Cover Removed Fig 13 1A Fig 13 1B Fig 13 1C The system must no...

Page 21: ...then dial back from there based on the performance of the system Once complete hit ENTER Scroll down to Exit and hit ENTER the initial setup is complete 7 Run an test run of the system to see if every...

Page 22: ...ted for approximately four 4 hours AFTER moisture is no longer detected To change the amount of After Run time adjust the dial labeled DELAY OFF to MIN or MAX to lessen or lengthen the After Run time...

Page 23: ...e SnowMeltz mat s 3 Be sure to follow local code for the correct gauge of wire for a dual pole 30 amp 240v circuit 4 Power to the M326A must be off before wiring the unit 5 Wire the green ground wire...

Page 24: ...Installation and Operation Manual Activator not configured or wired correctly Refer to specific instructions included with the activator purchased for use with this system Area activated continously A...

Page 25: ...stem to overheat and burnout Q Where should the activator sensor be located A Arial or ground sensors must be located in or close to the area s to be heated and must be able to detect moisture unabate...

Page 26: ...Use this grid to layout the SnowMeltz system...

Page 27: ...e had components not purchased from Heatizon Systems integrated into or connected to them 4 Any labor costs for removal of alleged defective part s and or reinstallation of replacement part s transpor...

Page 28: ......

Page 29: ...Information Owner s Name ________________________________________________________________________________________ Home Address _________________________________________________________________________...

Page 30: ......

Reviews: