5 Commissioning the system – Requirements
43
5 Commissioning the system
The heating system is initially commissioned by specialists from HDG
Bavaria or from an authorised HDG partner.
Commissioning includes an introduction to the operation and
maintenance of the heating system as well as measurements to
determine exhaust emissions and combustion performance.
5.1 Requirements
The following requirements must be met to ensure there are no
problems during commissioning.
•
The heating system has been filled with water as specified.
•
The heating system has been bled.
•
The pressure of the membrane expansion vessel has been
adapted to on-site conditions.
•
All required DIN EN 12828 safety devices have been installed and
are ready for operation.
•
The power supply to all components is ensured. (Makeshift
solutions are not sufficient!)
•
All doors and openings on the boiler and on the chimney
connection pipe have been checked for a proper seal.
•
Air supply for combustion has been provided.
•
A sufficient amount of fuel is available.
✎
See “Operating Manual Lambda Control”, Chapter “2
Commissioning the system”.
5.2 Procedure
S
WITCHING
ON
THE
HEATING
SYSTEM
✎
See also Chapter “6 Using the heating system”, section
“6.2 Switching on the heating system”.
Danger!
Material damage and injury due to incorrect commissioning
Commissioning the system requires comprehensive expertise. If
this commissioning is done by an untrained person, the heating
system could be damaged.
Only allow authorised specialists to perform the commissioning.
Summary of Contents for Navora 20
Page 1: ...hdg bavaria com HDG Navora 20 25 30 HDG Navora 40 45 50 Operation Manual ...
Page 2: ......
Page 77: ...77 NOTICE ...
Page 78: ...78 HDG Navora 40 45 50 Version 1 de HDG Bavaria GmbH 06 2008 NOTICE ...
Page 79: ......