IT 2002 Order No BA 93-66-2201 Issue 01.06.08
29
5.2.4 Drawn-Arc Capacitor-Discharge Stud Welding
With drawn-arc capacitor-discharge stud welding, the welding energy is taken from a
capacitor. As a result, welding currents are very high and welding times (< 10 ms) very
short. Normally, a weld pool protection is not required. The process is mainly used for
welding elements in a diameter range of up to 8 mm.
5.3
Welding Preparation
Read the safety instructions in chapters 1, 3 and 5.
Observe the workplace requirements (chapter 3, ”Starting-up").
Check all cables and connections for proper condition.
Replace immediately defective cables and cable connections to avoid electrical
shocks.
Check the chuck for proper seat (see operating manual of according welding
gun).
Before welding, make sure that the bellows are checked for damage and proper
seat.
5.4
High-strength Welds
The following must be removed both from the weld zone and the ground clamp
connection areas:
– paint, oil and any other impurities,
– rust,
– non-conductive coatings from surface treated workpieces.
Weld to smooth and flat surfaces only.
For welding to pipes or punched plates consult our responsible
application manager (address of customer service see page ii).
Summary of Contents for 93-66-2201
Page 1: ...IT 2002 Power Unit 93 66 2201 Operating Manual...
Page 8: ...viii IT 2002 Order No BA 93 66 2201 Issue 01 06 08...
Page 45: ...IT 2002 Order No BA 93 66 2201 Issue 01 06 08 45 Power unit type IT 2002 93 66 2201...
Page 47: ...IT 2002 Order No BA 93 66 2201 Issue 01 06 08 47 Basic set up complete IT 2002 88 16 268...
Page 49: ...IT 2002 Order No BA 93 66 2201 Issue 01 06 08 49 Front assembly complete IT 2002 88 16 269023...
Page 53: ...IT 2002 Order No BA 93 66 2201 Issue 01 06 08 53 Country module USA complete IT 2002 88 17 930...
Page 56: ...56 IT 2002 Order No BA 93 66 2201 Issue 01 06 08 8 3 Circuit Diagram...
Page 65: ...IT 2002 Order No BA 93 66 2201 Issue 01 06 08 65 Service Support...
Page 69: ......