HADEF EEE Installation, Operating And Maintenance Instructions Download Page 14

 

 

 

 

14 

  

5.52.707.00.01.02

 

11 Functional 

test 

 

Pos: 15.2.1 /1_HADEF/11-FUNKTIONSPRÜFUNG/Funktionsprüfung/Krane - Alle @ 2\mod_1287562125698_52.docx @ 16463 @  @ 1 

 

11.1 

Checks before initial start-up 

Design 

ƒ

  Check all screws and safety connections 

ƒ

The open-lying teeth of the crane trolley must be lubricated. 

11.2 Functional 

test 

Function - crane trolley 

ƒ

  Check properly running of the crane. 

ƒ

  Check the beam for obstacle-free running. 

ƒ

  Carefully move the crane to the end positions and check the positions of the end stops. 

Pos: 15.2.2 /1_HADEF/11-FUNKTIONSPRÜFUNG/Funktionsprüfung/Krane - Zusatz Druckluft @ 2\mod_1289228637562_52.docx @ 16673 @  @ 1 

 

ƒ

  Directions of movements must go conform to the symbols on the pendant control. 

Pos: 15.2.3 /1_HADEF/---ALLGEMEIN/Hinweise/Endschalter/HINWEIS - Endschalter: Funktion nur richtiger Bewegungsrichtung @ 0\mod_1177488210926_52.docx @ 5431 @  @ 1 

 

  

NOTICE!

 

The limit switch function will only work if the movement direction of the load (lifting - lowering) corresponds 
to the push buttons of the control switch. 
 

Pos: 16.1 /1_HADEF/12-INSTANDSETZUNG/*Ü1*/#. Kapitel - Instandhaltung @ 0\mod_1172647603139_52.docx @ 405 @  @ 1 

 

12 Maintenance 

 

Pos: 16.2.1 /1_HADEF/12-INSTANDSETZUNG/Allgemein/01.Allgemein @ 0\mod_1173251926256_52.docx @ 469 @  @ 1 

 

12.1 General 

All monitoring, servicing and maintenance operations are to ensure correct functioning of the equipment; 
they must be effected with utmost care. 

ƒ

  Only “qualified persons” may do this work. 

ƒ

  Servicing and maintenance work must only be done when the hoist is not loaded. 

ƒ

  Records must be kept of all test results and measures taken. 

Pos: 16.2.2 /1_HADEF/12-INSTANDSETZUNG/Allgemein/02.Überwachung @ 0\mod_1173254503420_52.docx @ 472 @  @ 1 

 

12.2 Monitoring 

The monitoring and servicing intervals stated are valid for operation under normal conditions and single-shift 
operation. In case of severe operating conditions (e.g. frequent operation with full load) or special 
environmental conditions (e.g., heat, dust, etc.), the intervals must be shortened correspondingly  

 

Pos: 16.3.1.1 /1_HADEF/12-INSTANDSETZUNG/Bremsmotor/Tabelle/Tabelle Krane E @ 2\mod_1287564518354_52.docx @ 16474 @  @ 1 

 

12.3 

Brake motor  

Motor power 

 

kW 

Brake 

 

Type 

Brake 

 

V DC 

Nom.  

brake torque 

Nm 

Nom.  

air gap 

mm 

Air gap 

max. 

mm 

 

 

mm 

0,37 

FDB 08 

180 

0,2 

0,6 

min. rotor thickness           4,5 

0,55 

FK 

200 

0,3 

0,6 

min. brake lining thickness    1 

0,75 

FDB 08 

180 

0,2 

0,6 

min. rotor thickness            4,5 

 

Pos: 16.3.2 /1_HADEF/12-INSTANDSETZUNG/Bremsmotor/Allgemein/Bremse -  alle @ 0\mod_1173350194807_52.docx @ 557 @  @ 1 

 

12.3.1 

Assembling the brake 

1  Insert the retaining ring (1) into the shaft slot. 
2  Insert the feather key (2) into the motor shaft. 
3  Fix hub (3) with retaining ring (1). 
4  Assemble the friction plate (4) if existent. 
5  Push the rotor (5) onto the hub (3). 
6  Lock the magnet body with the 3 fastening 

screws (6). 

7  Set air gap “a” (refer to “adjusting the air gap”) 
8 Assemble the dust-protection ring (7) if 

existent. 

9Electric connection 

 

 

Illustration 13   

Summary of Contents for EEE

Page 1: ...Single Girder Electric Overhead Travelling Crane Type EEE Pos 1 4 1_HADEF TITELSEITE Bauarten auch als Adapterkran 2 mod_1288102918176_52 docx 16586 1 also available as adapter crane Pos 1 5 1_HADEF T...

Page 2: ...ww hadef com Subject to changes Pos 4 1_HADEF ALLGEMEIN Allgemein 4 Inhaltsverzeichnis Inhaltsverzeichnis 1 2 0 mod_1171286846268_52 docx 56 1 Table of Contents 1 Information 3 1 1 Indications to dete...

Page 3: ...ertified quality assurance system as per ISO 9001 The production of components at our work is subject to strict intermediate checks After assembly each product is subject to a final test with overload...

Page 4: ...d other useful information Danger from electricity Danger from explosive area Pos 6 2 2 1 1_HADEF 2 SICHERHEIT Allgemein Sorgfaltspflicht des Betreibers 04 Sorgfaltspflicht des Betreibers 0 mod_117205...

Page 5: ...othes that are too big wide Pos 6 3 1_HADEF 2 SICHERHEIT Bestimmungsgem e Verwendung 01 Alle au er 380 2 mod_1300955165911_52 docx 18464 1 2 4 Appropriate use The permitted safe working load of the de...

Page 6: ...the immediate vicinity must be informed by calling to them Please pay attention to the regulations for load carrying devices UVV for both positive and non positive methods of attaching loads The lift...

Page 7: ...Pneuma Cranes acco dard the cran riage version lly Version A le the end ca ageous 2 mod_1288082417896_52 docx 16570 1 Adapter C cranes are s n beam can 2 mod_1290678435939_52 docx 17350 1 carriages ar...

Page 8: ...luding running wheels and travel drive Standard as welded version C As option available with screw fittings version A B Wheels Machined steel wheels with ball bearing and wheel flange Pos 8 3 3 2 1_HA...

Page 9: ...00 4747 4765 250 0 55 5891 10000 6000 1600 5126 5228 250 0 55 1704 9000 1600 5500 5488 250 0 55 2361 11000 1600 5714 6016 250 0 55 2915 12000 2200 5841 6143 315 0 75 3311 14000 2200 6077 6379 315 0 75...

Page 10: ...ng r the hoist M oist accordin motor driven iagram sembly a me rane embly Ad ly arriages ers with scre evices altern ble adapters screws tight dapter plates ersion A oles into the m rding to the t he...

Page 11: ...87534915_52 docx 440 1 ople that are n They mus that the oper g personnel 1 mod_1264760146475_52 docx 11700 1 wn control sw 1287553567138_52 docx 16427 1 t control 6 rgency stop ction switch g slow fa...

Page 12: ...duty cycle i e intermittent operation S4 40 ED as per VDE 0530 means that in a period of 10 minutes the motor can operate no matter the height of the load for 4 minutes It is therefore irrelevant whet...

Page 13: ...ine acc VDE 100 9 2 2 Control connection Control cable with connection plug as standards Plug in for setting in operation Changes at connection cable are only allowed by am expert 9 2 3 Cable connecti...

Page 14: ...y must be effected with utmost care Only qualified persons may do this work Servicing and maintenance work must only be done when the hoist is not loaded Records must be kept of all test results and m...

Page 15: ...devices out of operation and effect a General Overhaul Further use of the equipment is only allowed after a licensed qualified person has proofed that further use is possible without doubt and the co...

Page 16: ...eralyn SF 320 Ca tioned by ord uble ention to the th the equipm unit against arning note in working area d the chapter epair of faults of failures ple 2 1 TION d by wear o c must be r ge ls are life t...

Page 17: ...ace the starter relay Phase failure only direct control Find the cause and repair Motor does not brake or has excessive afterrunning Electric hoists and winches Switching error after intervention in t...

Page 18: ...easures are as above Also read the chapter Transport and storage 17 2 Final decommissioning disposal Measures are as above After disassembly ensure that the disposal of the equipment and any materials...