Release: the important coil inertia can drive the wire rolling after end welding. 

 

Open the gas. The machine is ready to operate. 

 

 

4-8)Commissioning of the cooling liquid group 

( GENEGYS 515 WSF) 

 
 

• 

Never operates the cooling group without filling the cooling liquid tank before the use of the machine.  

 

• 

Use the cooling liquid -25°C. 

 

• 

Fill the tank until the maximum level 

 

For first use,

 the cooling circuit must be bleeded from the water. To do this operation, you have 

to connect the blue connection of the contact batch (5 or 10 meters) on the blue connection of the MIG 
generator. Inject compressed air in the blue pipe of the contact batch to drive out the air bubble 
contained in the pump circuit.  

 

• 

The pump can be used.  

 

• 

Connect the blue and red connection of the contact batch to the generator and the wire feeder. 

 

• 

Control that the water circulation works correctly. 

 

• 

Check the cooling liquid level before each use of the unit and complete the liquid if necessary. 

 
 

Summary of Contents for GENEGYS 510 SF

Page 1: ...European standards Directive Low Voltage 73 23 CEE of 19th February 1973 decree n 98 1081 of 3rd October 1995 Directive electromagnetic compatibility 89 336 CEE of 3rd May 1989 This conformity is esta...

Page 2: ...the level of the plug PROTECTION OF EYES AND BODY 1 During the welding process the operator must be protected from the eventual flashes of the electrical arc with protection clothes like leather glove...

Page 3: ...f VOLTAGE or WIRE SPEED measurement Potentiometer of instructions wire speed except on GENEGYS 510 SF Selection indicator of value wire speed or voltage Selection indicator of value voltage or wire sp...

Page 4: ...ed wire feeder type WF Commutator on wire feeder choice Position I generator wire feeder origin Position II separated wire feeder WF 212 324 or 344 W in option Terminal application on weak Thickness c...

Page 5: ...save gas Button of gas drain it allows to avoid impurity during bottle replacement or after a long immobilization Commutator On Off Yellow indicator of thermal switching Button of spot time adjustment...

Page 6: ...re feeder and screw down bank connection by integrating the pipe in the frontside hole For GENEGYS 510 SF and GENEGYS 515 WSF machine the gas connection of the bank is uniquely made on front side Gas...

Page 7: ...the coil and put it on the support with taking care to block with base spin then screw down again the swivel For an application with a 5Kg coil or d 200 put the adapter between the support and the co...

Page 8: ...the cooling circuit must be bleeded from the water To do this operation you have to connect the blue connection of the contact batch 5 or 10 meters on the blue connection of the MIG generator Inject c...

Page 9: ...1 5 0 8 A3 A4 A5 70 100 2 4 4 6 I I 2 0 8 1 A5 A6 A7 90 130 3 5 6 8 I 3 0 8 1 B1 B2 120 160 4 5 7 11 I 4 5 1 1 2 B3 B4 B5 150 250 4 6 7 12 II 5 7 1 1 2 B6 B7 230 330 4 7 7 15 II 7 9 1 2 1 6 C1 C2 C3 3...

Page 10: ...EGAZ value This value can be modified by pressing on or If you press again on you will adjust the POSTGAZ time POS on the higher display If you press a third time you will adjust the late time to the...

Page 11: ...ntrol the earth cable connection and clamp state Control the torch gate The WIRE rubs down after the rollers Covering WIRE guide crushed Locking of the WIRE in the torch No capillary tube WIRE quick t...