3. Module Preparation and Installation
PNEG-902
Multi - Module Dryer Stacking
13
Lifting Upper Module
9. Attach a frame tie down (D61-0011) at each corner of the upper module frame using existing and
supplied 1/2" bolts (S-3728), washers (S-2120) and nuts (S-6493) as shown in
.
Figure 3N
10.Lift upper module and move into place over lower module. Use a guide line to keep module steady
Figure 3O
Frame tie down (D61-0011)
Always use proper lifting/hoisting equipment when assembling or
disassembling equipment.
Do not walk or stand under hoisted equipment.