General Overview
Topics Covered in this Chapter
Tools Required for Construction
Guidelines for Proper Storage of Grain Bin Materials Prior to Construction
Overview for a Typical Bin Installation
Guidelines for Construction Procedures and Lifting Jack Usage
Instructions for Stirring Devices
Guidelines for Placement of the Decal Sidewall Sheet
General Information
General information, overview and instructions needed before performing work.
Read this manual carefully. This manual will provide instructions on building the sidewall and stiffeners.
You will also need to consult other instructions in building the bin.
These include, but may not be limited to:
• A stiffener and sidewall gauge layout chart. If such a chart is not included with this manual, contact
GSI.
• Roof instructions must be followed. Roof instructions are included in this manual.
• Ladders, roof stairs, roof handrails and other products are covered by separate instruction manuals.
Consult the appropriate accessory manual. Inside ladder instructions are included in this manual.
• Aeration systems and transitions are to be installed according to the instructions provided with the
system or transition.
• It is critical that the anchor bolts are installed and spaced correctly.
Tools Required for Construction
General tools needed to perform this construction:
• Combination wrench set 7/16 in. to 1 in.
• Alignment punches 12 in. long
• 1/2 in. Drive socket set and ratchet
• Nail aprons or tool pouches to hold supplies
• Gloves for hand protection
• Tape measure
• 1/2 in. Drive electric or pneumatic torque gun with variable impact capabilities