![GSI Group PNEG-1204 Installation And Operation Manual Download Page 38](http://html1.mh-extra.com/html/gsi-group/pneg-1204/pneg-1204_installation-and-operation-manual_2275159038.webp)
6. Belting Assembly
38
PNEG-1204
Enclosed Belt Conveyor
Belt Tracking
Squareness of the Conveyor
1. Before tracking procedure is begun, each section should be square and straight so there is no
unequal weight distribution. Check conveyor intermediate sections for any extensive damage such
as cave-in sides, etc. Idlers should be checked for looseness. If idlers are loose, re-center and tighten
set screws on bearing lock collar.
2. After intermediate sections are bolted together, a chalk line should be strung along the sides of the
conveyor, making sure that it is in a straight line. Loosening bolts on the intermediate frames will
permit slight adjustment of the intermediate sections.
3. After conveyor has been installed, check to see if the unit is level (width wise). The conveyor must
be level for proper belt tracking.
Figure 6V
Ref #
Description
A
Bearing
B
Shims
C
Bearing Adjustment Bolts
D
Tail Section
E
Head Section