21
GROWSPAN
™
GOTHIC PRO GREENHOUSES AND SYSTEMS
Revision date: 06.06.18 113836_37_38_39PC
END PANEL INSTALLATION (continued)
In photo below, top of panel is removed using a power
tool equipped with a round cutting bit. Use rafter as a
guide for best results.
NOTE:
Actual greenhouse frame may differ.
5. Continue installing panels and aluminum profile in the
locations shown on the end panel diagrams (Quick
Start section) for the front and back end walls.
ATTENTION:
U-channel profile is installed along the
edges of the panels shown in the diagram below.
Cut upper panel
to proper length.
6. Continue with the
Double Door Assembly
procedures.
Install profile here.
DOUBLE DOOR ASSEMBLY
Materials and parts needed to assemble doors include:
• Door frames and polycarbonate panels
• Door hinges and latch hardware
• Aluminum U-channel (104213)
• End cap (104548)
• Tek screws (FA4482B & FA4484B))
• Neo-bonded galvanized washers (102921B)
ASSEMBLE AND ATTACH DOORS
1. Locate door frame (102923), assemble (if needed), and
place on a flat surface.
2. Select one 4' x 8' polycarbonate panel and trim it so
that length is one-quarter inch (1/4") shorter than length
of door frame.
3. Trim width of panel (if needed) so that it is one-quarter
inch (1/4") narrower than width of door frame.
NOTE:
Trimming panels as instructed will keep panel
flush with edge of door frame
after
aluminum profile
(104213) is installed.
4. Remove protective film. Mark UV-protected side if
needed. Install panels with UV-protected side to the
outside (toward the sun).
5. Center the panel on the door frame.
6. Use FA4484B Tek screws and neo-bonded galvanized
washers to attach panel to horizontal cross tube of the
door frame.
NOTE:
Attach panel in the locations shown in photo
to hold panel in place while installing aluminum profile
(104213) to the perimeter edge of panel.