0NO0R0004-#
LRR gangway installation manual
Page 6 of 11
Guard rail (
ITEM 2
) attachments between each other.
Guard rail (
ITEM 2
) attachments with the guard rails (
ITEM 3
).
•
Assembly of the skirting Lg600 (
ITEM 9
) on the guard rail (
ITEM 2
) using the skirting attachment (
ITEM 10
)
on the reverse side of the gangway entry. Use the HM8x25 w nuts in the fittings kit (
ITEM
11
).
Note: the skirting may be assembled either to the right or to the left of the boiler according to
the ladder position.
Attachment HM8x25
w
M8 nut
Attachment HM8x25
w
M8 nut
Guard rail
ITEM 2
Guard rail
ITEM 3
Guard rail
ITEM 2
Lower
attachments
Upper
attachments
Guard rail
ITEM 2
Skirting attachment
ITEM 10
Skirting Lg 600
ITEM 9
Attachment HM8x25
w
M8 nut
Attachment
4x HM8x25
w M8 nut
Platform
ITEM 1
Attachment HM8x25
w
M8 nut