6.4 Connection of Refrigerant Pipes
6.4.1 Precaution for connection
1)
Pipe connections should be follow the following rules:
ķ
Outdoor unit shall be installed close to the indoor unit, hence to minimize the length and bends
of connection pipes.
ĸ
The height gap of outdoor unit and indoor units should be as small as possible
2)
The brazing operation must be strictly in accordance with the process requirements. During the
installation, do not damage the pipeline.
6.4.2 The process of flaring
ķ
Using the tube cutter to cut the connecting pipe in the appropriate place and remove the burrs.
ĸ
Install the nut before the flaring operation.
Ĺ
Check the flared portion, whether there is fractured or not.
Fig. 12
6.4.3 Precaution for elbow operation
ķ
The elbow operation could be done by hands. Be careful and do not damage the pipe.
Fig. 13
ĸ
The bending diameter of the pipeline must be greater than 200mm. The connection pipe cannot
often be bent or straightened. Otherwise it will harden and crack.
Ĺ
If the thermal insulation of the refrigerant pipe is not removed, please do not bend the pipe.
Otherwise, it maybe leads the pipe to crack. It is better to make an incision with a knife in the
thermal insulation and removes it. After elbow operation is finished, recover the thermal
insulation with binding band.
6.4.4 The process of install refrigerant pipes
ķ
Remove the screw caps from the pipes.
ĸ
Align the flared end of copper tube with the center of pipe joint. Tighten the nuts by hands. (If
the flared end of copper tube and the center of pipe joint are not in coaxial, it is hard to tighten
the nuts by hands, please do not tighten it with spanners, because the screw thread may be
broken by force).
Ĺ
Tighten the flaring nuts with torque wrench until you hear a “click”. (The spanner and torque