CASTER AND LEVELER MOUNTING 

CAUTION

•  To install casters or levelers the enclosure must be tipped onto its 

  side. The enclosure can be very heavy; several people will be    

  required in this process. Please practice safe lifting techniques.

•  DO NOT lay the enclosure on its front or back, this may damage the 

  door hinges.

•  Removing doors and sides will help reduce the weight of the  

 

  enclosure.

•  Before tipping, remove the side panels to prevent damage to the  

  locks and latches. 

 

 

ADJUSTABLE LEVELER MOUNTING 

On the bottom of the cabinet there are eight threaded holes, two in each 

corner. The outside holes are threaded 1/2"-13 thds. and will accept 

the levelers. Once the levelers (7209-HD or 7209-4HD) are installed, 

the cabinet level can be adjusted with the use of a 5/8" open wrench 

when adjusting from the outside or a 3/8" closed wrench/socket when 

adjusting from the inside.

ANCHOR MOUNTING THRU HOLE

The middle .75 dia. thru holes are for securing the enclosure to the 

floor.  These holes will accept a standard concrete anchor if desired; the 

Seismic Anchor Kit (AK101) is suggested.

CASTER MOUNTING

The four inside holes in each corner are threaded 1/2"-13 thds. to 

accept the casters.

 

Be sure to thread the caster into the bottom of the 

cabinet until it is firmly seated.

 

.75 Thru holes

(4) Adjustable 

Levelers

Swivel Casters

Counter clockwise rotation will 

adjust the leveling glide up

Clockwise rotation will adjust 

the leveling glide down

Summary of Contents for GL720E-2432

Page 1: ...nclosures GL720E 2432 GL720E 2436 GL720E 2932 GL720E 2936 GL840E 2432 GL840E 2436 GL840E 2932 GL840E 2936 E Series Enclosures Installation Instructions UL60950 1 UL2416 E Series Equipment Cabinet Rack...

Page 2: ...the E Enclosure could result in equipment damage serious injury or possible death Only trained service personnel should be used to remove the enclosure from the pallet Also be sure you have a suffici...

Page 3: ...needed depending on configuration 50 M6 cage nuts 3 8 square and M6 screws 10 32 tapped rails available must be specified at time of order This user s manual This user s manual applies to the followin...

Page 4: ...ing enclosures before installation Sudden stops and starts excessive force obstructed routes and uneven floor surfaces may cause the enclosure to topple over Loading Equipment WARNING Only install equ...

Page 5: ...NG DOOR SWING HANDLE OPERATING DOOR SWING HANDLE INTERCHANGING DOOR HANDLES Door handles on all doors can be interchanged with any one of Great Lakes optional swing handles CH 02 three digit combinati...

Page 6: ...note The easy latch slam is not compatible with 3 point latching split doors ASSEMBLYOFSWING LATCHHANDLEONALLOTHERDOORS STANDARD MESH STEEL PLEXIGLAS AND PERIMETER VENTED DOORS 5 0 T H K Standard fla...

Page 7: ...hree hinge pins pull the door away from the enclosure To attach the door align all three hinges of the door to their respective hinge pins on the enclosure and slowly slide the door down until seated...

Page 8: ...MOUNTING SIDE PANEL REMOVAL Before removing the side panel pull apart the quick disconnect grounding wires The side panels are secured to the enclosure frame with two quick release latches and a keyed...

Page 9: ...3 thds and will accept the levelers Once the levelers 7209 HD or 7209 4HD are installed the cabinet level can be adjusted with the use of a 5 8 open wrench when adjusting from the outside or a 3 8 clo...

Page 10: ...TPE F TPE F10 TPE 2F10 Solid Perforated Three One 10 550 Two 10 550 75 CFM Fans CFM Fan CFM Fans BOTTOM PANELS There are several styles of panels available for the bottom of your E Series enclosure O...

Page 11: ...sure has two pairs 12 ga steel powder coated rails come installed with all standard frames at 19 EIA 310 E The 29 W E enclosure can be configured to 23 EIA mounting with an optional replacement bracke...

Page 12: ...he power strip into the corner post of the frame and then place one bracket between the top two outlets and install the 10 32 x 1 2 screw into the threaded hole in the frame Then place the other brack...

Page 13: ...nt Universal Power Strip Brackets in an E enclosure or cabinet extension measure the required mounting distance top to bottom install brackets then install power strip Spring Clips Tinnerman Clips 10...

Page 14: ...kit of 24 sections Fingers can be installed on the front or rear rails but front rails must be recessed 4 5 for proper installation It is recommended that each CM 47 be installed using 3 points of at...

Page 15: ...so available Additional horizontal bars can be installed alone without a vertical bar or in conjunction with a kit Additional vertical bars can only mount when at least two horizontal bars are already...

Page 16: ...e VCB 7236 Cable Management Bar Kit for 720E 36 enclosure VCB 8432 Cable Management Bar Kit for 840E 32 enclosure VCB 8436 Cable Management Bar Kit for 840E 36 enclosure VCB 72 Single Vertical Cable B...

Page 17: ...tallation in a Great Lakes E Enclosure is identical ZERO RMU MOUNTING ZR1 ZR2 Both ZR bracket kits fit on the 29 W E enclosure These allow for 0 RMU outside of the EIA rail pattern mounting of 19 rack...

Page 18: ...to the common building ground The kit contains one 48 L ground wire assembly and five 24 L ground wire assemblies Each assembly is made of two smaller wires that are connected this allows a Quick Dis...

Page 19: ...individual devices and components mounted within an enclosure to be grounded they must be connected to a copper bus bar Available copper bus bars include CBB 19 Copper Bus Bar for 19 rack mounting Is...

Page 20: ...FORM MS 5 02 58 REV 0 ETSI Associate Member Thank you for your business...

Reviews: