We recommend you assemble the pool between two or three persons and on a wind-free day. The use of gloves for the
installation is recommended for safety.
THE ENTIRE PROCESS SHOULD BE CARRIED OUT ON FIRM AND LEVEL
GROUND, BEFORE EXCAVATING THE FOUNDATION
EXCAVATION OF THE FOUNDATION (Z) FOR THE COLUMNS (C):
Dimension of the foundation: Z= 315cm
IMPORTANT:
When excavating the foundation, the rectangular space reserved for situating the AP that should be buried
5 cm and transversally fixed with their respective PG should be excavated(*). All the structural system should be perfectly
levelled (columns and internal structure, beams).
(*)
315
cm
315
cm
450
cm
15
cm
20
cm
Foundation
Columns
Z
Z
Z
C
C