Installation
8
3A3169E
Starting Pump
1.
Make sure the
supply line (G)
is connected and
there are no open lines for oil to leak out of the
pump outlet (E)
.
2.
Close the
oil supply shut-off valve (V)
.
3.
Turn on the
oil input supply pump/system (DD)
.
4.
Adjust
pressure reducing valve (U)
to limit the oil
inlet pressure to 80 psi (0.55 MPa, 5.5 bar).
5.
Slowly open the oil supply
shut-off valve (V)
.
6.
Remove the trapped air in the pump reservoir (K) by
slowly opening the cock valve (BB) until oil can be
seen coming out after all the air is released as
shown in F
7.
Close the cock valve (BB).
Supply Lines
1.
If there are multiple pumps on the air line, close the
air regulators (B2)
and b
leed-type master air
valves (F)
to all but one the pumps. If there is only
one pump, open its air regulator and bleed-type
master air valve.
2.
Open the
master air valve (F)
.
3.
Set the air pressure to each pump at the lowest
pressure needed to get the desired results. See
Recommended Pressure provided in
Table 1:
Lubricant Output and Pressure - US
or
Table 2:
Lubricant Output and Pressure - Metric
provided
on page 12.
4.
Remove trapped air in the
supply line (G)
by
removing a plug or opening a fitting on the furthest
end of the supply line. Run the pump until oil comes
out. After oil free of air comes out, close the line.
Feeder Lines (S)
Fill each
feeder line (S)
with lubricant prior to connect-
ing lines to the injector outlet.
Injectors (H)
For the following instructions, refer to Typical Installa-
tions, F
. 1, page 4, for the following instructions.
1.
Check each
injector (H)
for proper operation. The
injector stem should move when lubricant is dis-
charged.
2.
Adjust the injector output if needed to ensure that
the output volume discharged is sufficient.
F
IG
. 6
NOTICE
Always use lowest pressure possible to obtain desired
results.
Oil