Electric Reactor Kit Installation 

2

309969C

3.

Wait for heaters and fluid to cool.

4.

Remove back heater cover (C). See F

IG

. 1.

NOTE: Use dropcloth or rags to protect Reactor and 
surrounding area from spills. 

5.

Remove old parts.

a.

If replacing an existing rupture disk assembly 

(D), remove old assembly from heater inlet 

manifold (M). See F

IG

. 2.

b.

If converting heaters that do not have an exist-

ing rupture disk assembly (D), remove plugs 

from locations A and B shown in F

IG

. 2, using a 

3/8 allen wrench.

Assembly

1.

Apply pipe sealant and PTFE tape to rupture disk 
assembly (D) threads. See F

IG

. 2. Install as shown 

for applicable heater. Exhaust hole must be at bot-
tom, angled slightly toward outside of heater com-
partment.

2.

Apply 171001 Warning Label (L) to front heater 
cover, facing rear of Reactor. See F

IG

. 1.

Replacement Warning labels are available at no 
cost.

3.

Reinstall back heater cover (C). Return Reactor to 
service.

F

IG

. 1. Rear Heater Cover and 171001 Warning Label

C

TI3764a

Using a wrench on the rupture disk red housing can 
cause damage, resulting in a lower rupture pressure. 
To tighten the rupture disk assembly (D), use a 
wrench on the hex. Do not use a wrench on the red 
housing.

To avoid severe burns, do not operate Reactor with 
heater cover (C) removed.