![GORMAN-RUPP PUMPS 3D-B Installation, Operation, And Maintenance Manual With Parts List Download Page 8](http://html1.mh-extra.com/html/gorman-rupp-pumps/3d-b/3d-b_installation-operation-and-maintenance-manual-with-parts-list_2246812008.webp)
D SERIES
OM-01490
PAGE B - 1
INSTALLATION
INSTALLATION - SECTION B
Review all SAFETY information in Section A.
Since pump installations are seldom identical, this
section offers only general recommendations and
practices required to inspect, position, and ar
range the pump and piping.
For further assistance, contact your Gorman‐Rupp
distributor or the Gorman‐Rupp Company.
Pump Dimensions
See Figure 1 for the approximate physical dimen
sions of this pump.
OUTLINE DRAWING
Figure 1. Pump Model 3D‐B
PREINSTALLATION INSPECTION
The pump assembly was inspected and tested be
fore shipment from the factory. Before installation,
inspect the pump for damage which may have oc
curred during shipment. Check as follows:
a. Inspect the pump for cracks, dents, damaged
threads, and other obvious damage.
b. Check for and tighten loose attaching hard
ware. Since gaskets tend to shrink after dry
ing, check for loose hardware at mating sur
faces.
c. Carefully read all tags, decals, and markings
on the pump assembly, and perform all duties
indicated.
d. Check levels and lubricate as necessary. Re
fer to
LUBRICATION
in the
MAINTENANCE
AND REPAIR
section of this manual and per
form duties as instructed.
e. If the pump and
motor have been stored for
more than 12 months, some of the compo
nents or lubricants may have exceeded their
maximum shelf life. These
must be inspected
or replaced
to ensure maximum pump serv
ice.