background image

2

Remove the shipping bracket spanning the A-Coil apex to the rear of the wrapper on all models prior to installation.

The bottom duct flange for the supply plenum side is shipped unattached. Carefully insert the flange into bottom rail
and use a 5/16" screw to attach at the middle of the flange.

Attach coil to the furnace using hardware and brackets provided. (see Figure 3)

Attach plenum to coil. (see Figure 3)

Use tape or mastic to seal between coil and furnace, and also between coil and plenum.

FIGURE 3

(Installation of Furnace, Coil, and Plenum)

COIL

PLENUM

FRONT BRACKET

ACCESSORY

FURNACE

TOP & BACK
BRACKET
ACCESSORY

ACCESSORY

TOP & BACK

ACCESSORY

FRONT BRACKET

COIL

FURNACE

BRACKET

PLENUM

(Z-BRACKET WITH NARROW FURNACE)

Condensate Drain Piping - When coils are installed above ceilings, or in other locations where damage from condensate
overflow may occur, it is MANDATORY to install a field fabricated auxiliary drain pan under the coil cabinet enclosure. Drain
lines from the auxiliary pan must be installed and terminated so that the homeowner can see water discharges. A primary
condensate drain connection is located in the drain pan on the bottom of the coil / enclosure assembly. The female (3/4 fpt)
threaded fitting that protrudes outside of the enclosure is used for external connection.

Ensure drainpan hole is NOT obstructed.

To prevent potential sweating and dripping on to finished space, it may be necessary to insulate the condensate
drain line located inside the building. Use Armaflex® or similar material.

A Secondary Condensate D

rain Connection, now called for by many building codes, has been provided.

The drain lines are to be pitched 1/4" per foot to provide free drainage. Insulate drain lines to prevent sweating.
Trapped lines are required by many local codes. In absence of any prevailing local codes, reference requirement
from the Uniform Mechanical Building Code.

NOTE:  If secondary drain is not installed, the secondary access must be plugged.

FIGURE 4

(Drain Piping Installation)

Air Handler

3" MIN.

POSITIVE LIQUID SEAL REQUIRED

AT TRAP

Drain

Connection

2" MIN.

Summary of Contents for CH SERIES

Page 1: ...dering repair parts give the complete product model and serial numbers as stamped on the product Replacement parts for this product are avail able through your contractor or local distributor For the...

Page 2: ...female connections The connectors re quired can be 3 4 NPT male either PVC or metal pipe and should be hand tightened to a torque of no more than 37 in lbs to prevent damage to the drain pan connecti...

Page 3: ...sys tem is of sufficient design to ensure proper condensate re moval from the coil drain pan PITCH TOWARDS DRAIN 1 MIN TRAP CONDENSATE DRAIN CONN CONNECT DRAIN SAME SIZE AS ON UNIT OR LARGER Figure5 R...

Page 4: ...sulation RUBBER GROMMET SUCTION LINE WITH SPIN CLOSURE Figure8 Suction Line Grommet 11 Check fittings for leaks after complete installation Evacu ate and charge on the low side NOTE With the piston in...

Page 5: ...LLATION AND OPERATING INSTRUCTIONS FOR HORIZONTAL TWO WAY COILS CH SERIES IMPORTANT The United States Environmental Protection Agency EPA has issued various regulations regarding the introduction and...

Page 6: ...cabinet enclosure Drain lines from the auxiliary pan must be installed and terminated so that the homeowner can see water discharges A primary condensate drain connection is located in the drain pan o...

Page 7: ...he 13 16 nut 1 turn only to allow the high pressure tracer gas to escape No gas indicates a possible leak 2 After the gas has escaped remove the nut and discard the cap 3 Use a tube cutter to remove t...

Page 8: ...ficiency We have designed these units to significantly reduce the most frequent causes of product failure They are simple to service and forgiving to operate We use quality materials and components Fi...