2.5.3  INSTALLATION IN HYBRID SYSTEM FOR DESIGNATED CIRCUITS 

(

CONFIGURATION D

)

The TS-30 A can be installed between inverter (default) and a circuit panel supplied by a larger amp alternating power 

supply (dominant). 

1. Connect the inverter to terminals 7 and 8. 

2. Connect the 30-amp branch circuit to 5 and 6.

3. Connect the designated circuit panel to the output terminals to connections 3 and 4.

The inverter will only supply the load in the absence of the 50-amp power supply, in which case, only the load designated 

to the 30-amp branch circuit is supplied. The timer delay bypass switch on the TS-30 should be in the ON position.

3. 

OPERATIONAL TESTING

READ AND FOLLOW ALL SAFETY INSTRUCTIONS

The following diagrams on pages 12-15 show how the IC Series inverter/charger is typically installed in a mobile RV application.  

The diagrams show where the Inverter/Charger is installed and how the mobile power system can be integrated with a Go 

Power! RV Solar Kit (sold separately by Go Power; please contact us directly.)

1.  Plug in the power cord. If the main panel circuit breakers are switched on, RV load should operate normally. Unplug the 

power cord.

2.  Start the generator. There is a pre-programmed 20-30 second delay in the transfer switch. The delay is designed to allow 

the generator a brief warm-up period. When the delay completes its cycle the switch should engage and the RV load 

should operate normally. An audible click should sound as the switch engages.

3.  Shut down the generator. As the generator winds down the switch should disengage without chatter or cycling. An audible 

click should sound as the switch disengages.

4.   Plug in the power cord. Start the generator. After the preprogrammed delay, the switch should transfer power automatically 

from the power cord to the generator. Listen for the audible click as the switch transfers, as there will likely be no other 

indication that the switch has engaged. Shut down the generator and unplug the power cord.

5.  On transfer switch arrangements with three power supplies, plug in the power cord, start the generator, and turn on the 

inverter. With all three supplies energized at the same time, the switch will select the generator for the primary supply choice.  

Shut down the generator. The switch will transfer to the power cord. Unplug the power cord. The switch will transfer to 

the inverter. The inverter should always be connected so that it is only selected in the absence of both the other supplies.

3. OPERATIONAL TESTING

The powercord is a 15, 20 or 30 amp line from 

the main panel.

#1

#2

Summary of Contents for GP-TS-30

Page 1: ...nsfer Switch User Manual GP TS 30 2020 Go Power Worldwide Technical Support and Product Information gpelectric com Go Power 201 710 Redbrick Street Victoria BC V8T 5J3 Tel 1 866 247 6527 MOBI_MAN_GP T...

Page 2: ...formation size install date battery type Product Packaging Please safely store the packing the IC Series was delivered in or recycle the packaging components as outlined below LDPE Low Density Polyeth...

Page 3: ...ric com page 3 CONTENTS 1 INTRODUCTION 4 2 INSTALLATION 4 3 OPERATIONAL TESTING 7 4 TROUBLESHOOTING 8 5 HI POT TESTING 9 6 GENERATOR NOTE 10 7 MEDICAL APPLIANCES 10 8 CAUTION 10 9 WARNINGS 10 10 WARRA...

Page 4: ...mpartment designed for storage of flammable liquids such as gasoline 2 3 ELECTRICAL PREPARATION Any numbered knockout on the TS 30 can be used for installation Choose a knockout that will facilitate i...

Page 5: ...IONS A B 1 Connect the power cord leads to terminal 7 and 8 on the narrow end of the relay these are the normally closed N C contacts See Diagram 1 on page 6 for numbered locations 2 Connect the gener...

Page 6: ...allow any other supply to dominate the inverter and the inverter output will pass through the normally closed contacts of the switch This allows the inverter to operate only in the absence of the othe...

Page 7: ...enerator There is a pre programmed 20 30 second delay in the transfer switch The delay is designed to allow the generator a brief warm up period When the delay completes its cycle the switch should en...

Page 8: ...o drop out at which point the voltage will rise to the pre in rush level The contacts will chatter when the A C compressor kicks in however the voltage may read normal Most meters are not fast enough...

Page 9: ...hould be performed from either the transfer switch output or from the main panel Test as follows 1 Turn on all circuit breakers in the panel 2 Make sure the generator is off 3 Make sure the power cord...

Page 10: ...tion may cause arcing In addition the act of turning on a light switch or unplugging the cord on an electrical appliance can cause a spark which can ignite any combustible liquids or vapors Therefore...

Page 11: ...lting from but not limited to Misuse and or abuse neglect or accident Exceeding the unit s design limits Improper installation including but not limited to improper environmental protection and improp...

Page 12: ...2020 Go Power Worldwide Technical Support and Product Information gpelectric com Go Power 201 710 Redbrick Street Victoria BC V8T 5J3 Tel 1 866 247 6527 MOBI_MAN_GP TS 30 RevE...

Reviews: