Required personnel qualifications
Activity
Personnel
Integration in control system
Specialist staff
Plant designer
Installation/electrical
connection/bringing into service
Specialist staff
The equipment may only be installed, wired
and brought into service by qualified and
competent staff.
Operation
Boiler service technician
Staff trained by the plant operator.
Maintenance work
Specialist staff
Maintenance and conversions may only be
performed by authorised staff who have
undergone specific training.
Refits
Specialist staff
Persons trained by the plant operator to work
with pressure and temperature.
Fig. 1
Notes on product liability
The manufacturer cannot accept any liability for damages resulting from improper use of the equipment.
Check the current output regularly
Check level electrode function at least once a year by bringing the system to the minimum and/or maxi-
mum water level (T1 = 1 year).
The test function is initiated on site using the integrated rotary knob on the terminal box, see page 42.