Same as when digging a
horizontal
reference,
the
screen and the LED display
will
indicate
the actual
difference of your bucket tip
to the reference.
Digging a trench with 2% slope
Method 1: Using the ground as reference
Short-press the Slope Symbol
Dial-in 2.00% and confirm
with the checkmark
Place the tip of the bucket on
your final elevation (ground)
then Short-press one the
elevation symbol
Dial-in “0” and confirm with
the checkmark
Note: Without 2D
sensor, you have to dig
straight, not leaving
the slope’s axis by
rotating the cab. A slew
of the cab out of the
axis will instantly lead
to a loss of accuracy!
16
Summary of Contents for EZDig T
Page 1: ...Manual Version 2 00 Software Version 3 5 1 User Manual EZDig T Menu Language English 1 ...
Page 5: ...Digging a hole Method 1 Using the ground as reference 5 ...
Page 7: ...Digging a hole Method 2 Using surveyor stake as reference 2 50m Surveyor Stake 7 ...
Page 9: ...Digging a 5m wide hole 5m Surveyor Stake 9 ...
Page 15: ...Digging a trench with 2 slope Method 1 Using the ground as reference 15 ...
Page 26: ...Changing the elevation Method 2 Working with a rotating laser 0 10m 4 71m 4 61m 26 ...
Page 36: ...36 ...