GE-R4 INSTALLATION
GE-R4
Section B-6
General installation guidelines
GE-R4 Module
-
It is recommended to install the module unit in a hallway to limit the GE-R4 exposure
to noxious gases.
- In order to avoid condensation problems inside the module, it is recommended to
install the GE-R4
on an inside wall. If it is not possible, use spacers to have an air gap
between the wall and the GE-R4.
- It is required to install the GE-R4 right side up with the cable entry holes facing
down.
- The enclosure is watertight, but do not spray water or submerge the GE-R4 in water.
Cover it carefully with plastic when cleaning the room.
- The GE-R4 should be installed in easy-access location but away from damaging
elements (heat, cold, water, direct sunlight, …).
-
Do not drill the face, the side, the top or the underside of the control.
- Do not install the GE-R4 module near high-voltage equipment, power supply or
transformer.
Electrical Cables
-
All electrical cables must be installed according to local wiring codes.
- Use separate conduits for the low voltage cables (communication) and the high
voltage cables. There must be at least 30 cm (1 foot) between low-voltage and high-
voltage conduits.
- If a low voltage cable has to cross over a high voltage cable, make this crossing at
90°.
-
It is prohibited to use overhead cables outside the building.
Electrical Power
- Protection from electrical surges should be included in the planning of each
installation.
-
Every module should have a separate breaker to avoid possible problem.
www.monitrol.com