Generac Power Systems PV Link 010023 Installation Manual Download Page 15

Installation Manual for PV Link and SnapRS

11

Section 4 PVRSS Compliance Guidelines

2011 NEC and Older Editions 

2011  NEC  and  older  editions  do  not  require

PVRSS compliance. 

NOTE: 

The  PV  Link  will  still  provide  2014

NEC compliant PV Rapid Shutdown.

2014 NEC 

The  2014  NEC  690.12  introduced  a  new

requirement for PV systems that is commonly

referred to as PV rapid shutdown. 

To meet 2014 NEC compliance:

1.

Install the PWRcell Inverter as specified in

the  Generac  PWRcell  Inverter Installation

Manual.

2.

Install the PV Link as specified in this man

-

ual.

3.

The  DC  disconnect  under  the  PWRcell

Inverter  cover  labeled  PV  by the  installer

can  be  used  as  the  PVRSS  initiation

device. See  Rapid  Shutdown  in the Gen

-

erac  PWRcell  Inverter  Installation  and

Owner’s Manual for more information.

4.

The  Remote  STOP  terminals  under  the

PWRcell  Inverter  cover  labeled  “STOP”

can  be  used  for  PVRSS  initiation.  If  the

PWRcell  system  includes  PWRcell  Bat

-

tery/ies,  the  battery/ies  must  have  a  bat

-

tery management unit (BMU) with optional

STOP  terminal  hardware.  See  Generac

PWRcell  Battery  Installation  and  Owner's

Manual for instructions. An external actua

-

tor  must  be  provided  by  the  installer.

Appropriate  signage,  in  compliance  with

the NEC must be provided by the installer

indicating the function of the external actu

-

ator. 

Rapid shutdown response time is less than 10

seconds.

2017 and 2020 NEC

The  2017  and  2020  NEC  have  PVRSS

requirements  mandating  the  need  to  reduce

voltages of controlled conductors to less than

80  VDC  within  the  array,  and  less  than  30

VDC outside the array, as well as some speci

-

fication for the location of the PVRSS initiator

and its labeling. 

To meet 2017 and 2020 compliance:

1.

The  2017  and  2020  NEC  requires  the

PVRSS  initiator  be  located  at  a  readily

accessible location outside the building. 

– The DC disconnect under the PWRcell

Inverter  cover  labeled  PV  by  the

installer can be used as the PVRSS ini

-

tiation device.

– An external actuator, connected by the

installer  to  the  PWRcell  Inverter's

STOP  terminals  can  be  used  as  the

PVRSS initiation device. If the PWRcell

system  includes  PWRcell  Battery/ies,

the  battery/ies  must  have  a  battery

management  unit  (BMU)  with  optional

STOP terminal hardware. See Generac

PWRcell  Battery  Installation  and

Owner's Manual for instructions.

NOTE: 

Provide signage indicating the PVRSS

initiation device  is the REbus PV DC discon

-

nect  located  under  the  front  cover  of  the

inverter, or the external actuator connected to

the STOP terminals.

– An  externally  mounted  PVRSS  initia

-

tion device is required to be installed at

a  readily accessible location when the

PWRcell  Inverter  is  installed  within  a

one- or two-family dwelling unit.

NOTE: 

Provide  signage  indicating  where

PVRSS  initiation  devices  are  located.  Note

that if the inverter is installed in the appropri

-

ate outdoor location it may satisfy this require

-

ment.

2.

Provide  signage  complying  with  section

690.56(C)  of the NEC  (NFPA 70),  stating

all conductors are controlled.

NOTE: 

Install  one  SnapRS  to  the  negative

whip (-) of each PV module connected to the

PV Link.

3.

Install the PV Link. See 

Installation Guide

-

lines

 for more information.

Upon initiation of rapid shutdown, both inputs

and outputs of the PV Link are controlled to be

less than 80 VDC. PV Link outputs are further

controlled to be less than 30 VDC. Rapid shut

-

down response time is less  than  30  seconds

in accordance with section 690.12 of the NEC

(NFPA 70).

Summary of Contents for PV Link 010023

Page 1: ...d in a critical life support application Failure to adhere to this warning could result in death or serious injury Register your Generac product at https pwrfleet generac com 1 888 GENERAC 888 436 372...

Page 2: ...ty to perform all safety checks to verify that all maintenance for safe operation is performed promptly and to have the equipment checked periodically by an ASD Normal maintenance service and replacem...

Page 3: ...ormation 7 Component Locations 7 Section 3 Installation Design 9 Installation Design Worksheet 9 Section 4 PVRSS Compliance Guidelines 11 Section 5 Mounting and Connecting 13 Installation Guidelines 1...

Page 4: ...This page intentionally left blank...

Page 5: ...erating technique that the manufacturer does not specifically recommend verify that it is safe for others and does not render the equipment unsafe Throughout this publication and on tags and decals af...

Page 6: ...o ensure the completed PV system meets the rapid shutdown functional requirements This equip ment must be installed according to the manu facturer s installation instructions 000191 DANGER Automatic s...

Page 7: ...s injury equipment and property damage DANGER 000152 DANGER Electrocution Verify electrical system is properly grounded before applying power Failure to do so will result in death or serious injury 00...

Page 8: ...4 Installation Manual for PV Link and SnapRS This page intentionally left blank...

Page 9: ...voltage VDC 420 open circuit Nominal output REbus DC nanogrid 380 VDC data Maximum output current continuous A 8 Standby power W 1 Topology Boost converter Protections Ground fault protection arc fau...

Page 10: ...nk is intended for use with 60 cell 72 cell or 96 cell residential DC solar modules Solar modules must not require positive or negative grounding as this would interfere with PLC communications NOTE O...

Page 11: ...NEC requires rapid shutdown only on the conductors leaving the PV array The 2017 and 2020 NEC require rapid shutdown at the PV module level and on the conductors leaving array PV Link is a PV rapid sh...

Page 12: ...8 Installation Manual for PV Link and SnapRS This page intentionally left blank...

Page 13: ...e limit 3 Divide the PV Link Vmp Voltage at Maxi mum Power by the panel Vmp and round down to determine the number of panels that can be connected in series to the PV Link without exceeding maximum po...

Page 14: ...10 Installation Manual for PV Link and SnapRS This page intentionally left blank...

Page 15: ...cation of the PVRSS initiator and its labeling To meet 2017 and 2020 compliance 1 The 2017 and 2020 NEC requires the PVRSS initiator be located at a readily accessible location outside the building Th...

Page 16: ...12 Installation Manual for PV Link and SnapRS This page intentionally left blank...

Page 17: ...G ELECTRIC SHOCK HAZARD THE DC CONDUCTORS OFTHIS PHOTOVOLTAIC SYSTEM ARE UNGROUNDED AND MAY BE ENERGIZED ELECTRIC SHOCK HAZARD DC OUTPUT CONDUCTORS MAY BE ENERGIZED REGARDLESS OF SUN EXPOSURE CAUTION...

Page 18: ...lation or flagging Mark negative REbus field wiring leads with blue insulation or flagging Connect multiple optimizers in parallel using MC4 branch connectors or a com biner box Connecting PV Modules...

Page 19: ...he input of the PV Link NOTE Install SnapRS devices prior to secur ing PV modules to the racking To install SnapRS devices 1 See Figure 5 5 For each PV module in the PV string connect the positive end...

Page 20: ...st be one SnapRS device for each module in the array Additionally the String Count set ting on the PV Link device page must be set to 2 Figure 5 6 Single PV Substring with Parallel Series Inputs and S...

Page 21: ...s Manual for more information on sys tem modes and commissioning To enable and commission PV Link Ensure REbus are connected with correct polarity to each PV Link Ensure each PV Link has a low resis t...

Page 22: ...cription PLM Channel 1 12 1 Channel for REbus communications All devices in a sys tem must use the same channel except REbus Beacon Vin Strartup 60 135 Volts 135V Minimum input voltage from the PV sub...

Page 23: ...orking properly When an arc fault is detected the status message reads Arc Fault To conduct an AFD test 1 On the PWRcell Inverter control panel use the left or right arrows to scroll to the page for t...

Page 24: ...20 Installation Manual for PV Link and SnapRS This page intentionally left blank...

Page 25: ...ce If the PV Link is not operating as expected or if a PV Link error message appears on the Generac PWRcell Inverter control panel LCD display contact the nearest Independent Authorized Service Dealer...

Page 26: ...22 Installation Manual for PV Link and SnapRS This page intentionally left blank...

Page 27: ...Polarity Check REbus Wiring Ground May Need to Check REbus Fuses Known PV Link Offline A PV Link that has communicated with the inverter previously shows offline at its device page when it s connecti...

Page 28: ...performed on SnapRS devices in the field However some simple digital multimeter DMM checks can confirm the general health of a SnapRS device DMM Red to SnapRS DMM Black to SnapRS Resistance reads 300...

Page 29: ...Installation Manual for PV Link and SnapRS 25 This page intentionally left blank...

Page 30: ...26 Installation Manual for PV Link and SnapRS This page intentionally left blank...

Page 31: ......

Page 32: ...ights reserved Specifications are subject to change without notice No reproduction allowed in any form without prior written consent from Generac Power Systems Inc Generac Power Systems Inc S45 W29290...

Reviews: