Installation Guidelines for Air-Cooled Generators
47
Section 10
Installation Diagrams
10.1 — Installation Drawing
914 [36.0]
MINIMUM OPEN AREA
ON SIDES AND FRONT
457.2
[18.0]
76.2 [3.0]
PEA GRAVEL
MINIMUM
1229.5
[48.4]
1226
[48.3]
732.5
[28.8]
637.6
[25.1]
642
[25.3]
300.4
[11.8]
179.0
[7.0]
560.0
[22.0]
353.7
[13.9]
1154.0
[45.4]
446.6
[17.6]
389.7
[15.3]
36.0
[1.4]
44.8
[1.8]
LEFT SIDE VIEW
REAR VIEW
"DO NOT LIFT BY ROOF"
**ALL DIMENSIONS IN:
MILLIMETERS [INCHES]
A CONCRETE PAD
OPTIONAL MOUNTING TO
HOLE LOCATIONS FOR
TOP VIEW
16.0 [5/8] DIA. CLEARANCE
HOLE (2) PLACES,
3/8 DIA. MASONRY ANCHOR
BOLTS RECOMMENDED
AIR INTAKE
AIR OUTLET
AIR INTAKE
FUEL INLET - 15KW (1/2" NPT)
REQUIRED FUEL PRESSURE: NATURAL GAS : 3.5-7" WATER COLUMN
LIQUID PROPANE (VAPOR) : 10-12" WATER COLUMN
GROUND LUG
GROUND STUD
CABLE ACCESS HOLE
FRONT VIEW
RIGHT SIDE VIEW
FRONT OF UNIT
10.0 [3/8] DIA. CLEARANCE
HOLE (2) PLACES,
3/8 DIA. MASONRY ANCHOR
BOLTS RECOMMENDED
A CONCRETE PAD
OPTIONAL MOUNTING TO
HOLE LOCATIONS FOR
30.2 [
1.2]
LIFTING HOLES 4 CORNERS