3.1.5.11 Installation and labelling of parts delivered separately
(Handling instructions)
Mounting of the designation: on the evaporator
Fig.23:
Labelling of the parts delivered separately
1
(2045) Resistance thermometer - secondary refrigerant inlet temperature
2
(2000) Evaporator
3
(2050) Flow monitor
4
(2040) Resistance thermometer - secondary refrigerant - outlet temperature
Importance of the labels
Before start-up ensure that the parts delivered separately are installed in the pip-
ing circuit:
1.
Remove the parts from the packaging.
2.
Install the components according to the figure.
Notice
The delivery includes additional parts for the heat carrier or cooling medium
circuit. These parts must then be used accordingly.
► Note the hints given in the chapter “Start-up/water piping”.
3.2
Functional description
GEA RedGenium heat pumps are used for hot water provision by heating of the
heat carrier as well as cold water or cold brine cooling for air conditioning or for
industrial processes.
Description
Functional description
L_151511_2
19.12.2019
49
Summary of Contents for RedGenium
Page 6: ...L_151511_2 6 19 12 2019 ...
Page 8: ...L_151511_2 8 19 12 2019 ...
Page 14: ...L_151511_2 14 19 12 2019 ...
Page 118: ......