SecoGear – Installation, Operation and Maintenance Manual 41 of 56
The VCB must be open and in the DISCONNECTED/ TEST position
before proceeding.
1. Check that the position indicator flag in lower right front
corner of compartment shows DISCONNECTED/TEST.
2. Ensure that the spring energy is discharged. Check that
indicators on the VCB front cover show DISCHARGED
and OPEN.
3. Disconnect secondary control power plug.
4. Position the lift truck in front of the switchgear
compartment, and rotate the lift truck crank handle to
adjust the height of the lifting platform such that the ends
of the lift arms align with the guide slots just below the
VCB rails in the switchgear compartment. (Turn clockwise
to raise, counterclockwise to lower.)
5. Push the truck forward so that the transfer truck arms fully
engage in the switchgear rail guide slots and the rail stops
engage the switchgear. Lock the lift truck in position by
pressing down on the truck locking pedal, Figure 5-13.
6. Engage the lift truck compartment interlock to secure
the truck to the switchgear compartment.
7. Push the two locking handles on the front of the
VCB inward to unlock the VCB from the switchgear
compartment, Figure 5-17.
8. Pull the VCB forward onto the lift truck rails and lock
in position on the lift truck using the locking tabs on
both sides of the VCB. Ensure they engage and lock into
position, 5-5.
9. Release the lift truck compartment interlock.
10. Release the floor lock of the lift truck, Figure 5-7, and
move the lift truck away from the switchgear.
11. Lower the VCB to the ground.
Removing the Circuit Breaker
Racking the Circuit Breaker to Connected Position
When racking the VCB from CONNECT to DISCONNECT,
or DISCONNECT to CONNECT, do not stop or pause at
any intermediate position. Failure to engage in either
CONNECT or DISCONNECT position will render the
VCB inoperable.
CAUTION
1. Connect the secondary plug of the VCB into the socket
at the top of the switchgear compartment and lock it,
Figure 5-24 and Figure 5-25.
Figure 5-24. Release Secondary Plug from VCB
Figure 5-25. Insert Secondary Plug and Lock into Switchgear Compartment Socket
2. Make sure the VCB is in open position. If it is closed, press
the manual open pushbutton.
3. Close the door and insert the racking handle into the
racking access hole located at the bottom of the door,
Figure 5-26 and Figure 5-27, until the racking socket is
engaged with the racking drive screw.
4. Turn the handle clockwise (approximately 20 turns) until
it cannot be rotated any further.
Do not over torque the racking handle, applied force
should not exceed 22.12 ft lb (30 N/m)
CAUTION
When it makes a clicking sound, the VCB is now in the
Connected position. The VCB position indicator will change
the status from “TEST” to “CONNECTED”, Figure 5-29 through
Figure 5-31.