STEP 1  

Prepare Installation Area by Removing AZ75/AZ85 Unit

WARNING

Risk of Electrical Shock, can cause injury or death.  Before servicing, 

switch power off at the service panel and lock the area to prevent power 

from being switched on accidentally.

To remove the AZ75/AZ85 series unit:

 1.  

Disconnect the power coming into the unit from the main breaker or 

closet mounted disconnect.

 2.  

Remove the front case panel.

 3.  

Unplug the 9-pin yellow connector and disconnect the wall thermostat 

connection.

 4.  

Fully loosen the 4 adjustable screws on the top cover and disconnect 

the top duct work from the unit.

 5.

  Remove the front and or side case-to-unit grounding screws, if present.

 6.

  Slide the unit out of the case.

 7.

  Disconnect all of the drains.

 8.

  Remove the bolts holding the case to the platform (if present).

 9. 

 Remove the 6 screws securing the case to the plenum.

10.

 Remove the case.

11.

 Remove the platform, if needed.

Inside 

Wall

Rigid

Ductwork

Access 

Panel or 

Closet Door

Existing  

Wall Plenum

When complete the closet area 

should look like this.

STEP 2  

Install and Connect the Transition Plenum to the Existing Wall Plenum

NOTE:  The Drain pan must be installed into the transition plenum prior to screwing the transition plenum to the 

existing wall plenum.

 1.  

Before mounting the transitional plenum, install a piece of precut insulation to the bottom of the transitional plenum. 

Insulation should be installed flush with the front side of the transitional plenum and overhang slightly on the other 

side.

 2.  

Align drain pan outlet with the cutout in the bottom of the transition plenum.  Drop drain pan into place.

 3.  

Place the transitional plenum in front of the existing wall plenum with the flange side facing away from the wall 

plenum.

 4.  

Align the transitional plenum mounting holes to the mounting holes on the existing wall plenum.  The top of the 

transitional plenum should be even with the top of the existing wall plenum.

 5.

  Attach the transitional plenum to the wall plenum with the 6 supplied screws.

 6.

  Install the 3 remaining pieces of insulation to the top and sides of the transitional plenum.

Align  

Mounting 

Holes

Align Front 

Edges

Drain Pan

Outlet

Inside 

Wall

Rigid

Ductwork

Flush with 

top of 

existing 

wall plenum 

Flange

Insulation

Overlap

Drain Pan

Summary of Contents for RAVWP6

Page 1: ...ir conditioner with a new AZ90 91 series vertical air conditioner Differences in chassis designs between the AZ75 AZ85 series and AZ90 91 series require careful installation planning Changes in drain exit locations and drain routing electrical connections platform height conditioned air duct location and additional space requirements for installation of RAVTRANS kit are all items that need to be c...

Page 2: ...rea should look like this STEP 2 Install and Connect the Transition Plenum to the Existing Wall Plenum NOTE The Drain pan must be installed into the transition plenum prior to screwing the transition plenum to the existing wall plenum 1 Before mounting the transitional plenum install a piece of precut insulation to the bottom of the transitional plenum Insulation should be installed flush with the...

Page 3: ...ition plenum the sealing gasket should be lubricated with soapy water or similar solution to reduce the friction between the side of the unit and the gasket 2 Refer to the installation instructions that came with the unit to complete the installation Platform height varies by chassis size see below for details Printed in the United States Inside Wall Rigid Ductwork Platform Surface Platform Surfac...

Page 4: ...ans la conception de la carrosserie entre les séries AZ75 AZ85 et la série AZ90 91 exige une planification minutieuse de l installation Des modifications dans les sorties et la trajectoire du drainage les connexions électriques la hauteur de plateforme l emplacement des conduits d air et les dégagements supplémentaires requis pour l installation de la trousse RAVTRANS sont tous des éléments dont i...

Page 5: ...accès ou porte de l armoire Plenum mural existant Une fois terminée la zone de l armoire devrait ressembler à ceci ÉTAPE 2 Installation et raccordement du plenum de transition au plenum mural existant REMARQUE Le plateau de drainage doit être installé dans le plenum de transition avant de visser ce dernier dans le plenum mural existant 1 Avant de monter le plenum de transition posez une pièce d is...

Page 6: ...être lubrifié avec de l eau savonneuse ou une solution similaire afin de réduire la friction entre le côté de l appareil et le joint 2 Reportez vous aux instructions d installation incluses avec l appareil pour compléter l installation La hauteur de la plate forme varie selon la taille du châssis voir ci dessous pour plus de détails Imprimé aux États Unis 1 1 2 po Petite plate forme de plate forme...

Reviews: