GE Multilin
C60 Breaker Protection System
5-41
5 SETTINGS
5.2 PRODUCT SETUP
5
The DNP / IEC 60870-5-104 point lists always begin with point 0 and end at the first “Off” value. Since DNP / IEC
60870-5-104 point lists must be in one continuous block, any points assigned after the first “Off” point are ignored.
Changes to the DNP / IEC 60870-5-104 point lists will not take effect until the C60 is restarted.
l) IEC 61850 PROTOCOL
PATH: SETTINGS
PRODUCT SETUP
COMMUNICATIONS
IEC 61850 PROTOCOL
The C60 Breaker Protection System is provided with optional IEC 61850 communications capability. This
feature is specified as a software option at the time of ordering. See the
Order Codes
section in chapter 2
for details.
IEC 61850 messaging can form part of protection schemes. Consider 61850 settings with the same criticality as
protection element settings. To ensure reliable performance of protection schemes utilizing 61850 messaging, it
can be desirable to route 61850 traffic on a separate port from SCADA communications, or to use redundant, inde-
pendent ports, and a high speed network recovery method, such as PRP.
The C60 supports the Manufacturing Message Specification (MMS) protocol as specified by IEC 61850. MMS is supported
over two protocol stacks: TCP/IP over Ethernet. The C60 operates as an IEC 61850 server. The
Remote Inputs and Out-
puts
section in this chapter describe the peer-to-peer GSSE/GOOSE message scheme.
The EnerVista software includes an interface that is compatible with firmware versions 5.0 to 7.2 to configure subscribers.
Use the Simplified GOOSE Configurator in the Offline Window area.
IEC 61850 PROTOCOL
GSSE / GOOSE
CONFIGURATION
MESSAGE
SERVER
CONFIGURATION
MESSAGE
IEC 61850 LOGICAL
NODE NAME PREFIXES
MESSAGE
MMXU DEADBANDS
MESSAGE
GGIO1 STATUS
CONFIGURATION
MESSAGE
GGIO2 CONTROL
CONFIGURATION
MESSAGE
GGIO4 ANALOG
CONFIGURATION
MESSAGE
GGIO5 UINTEGER
CONFIGURATION
MESSAGE
REPORT CONTROL
CONFIGURATION
MESSAGE
XCBR
CONFIGURATION
MESSAGE
XSWI
CONFIGURATION
NOTE
NOTE
NOTE
Summary of Contents for C60
Page 10: ...x C60 Breaker Protection System GE Multilin TABLE OF CONTENTS ...
Page 30: ...1 20 C60 Breaker Protection System GE Multilin 1 5 USING THE RELAY 1 GETTING STARTED 1 ...
Page 420: ...5 284 C60 Breaker Protection System GE Multilin 5 10 TESTING 5 SETTINGS 5 ...
Page 466: ...8 4 C60 Breaker Protection System GE Multilin 8 1 FAULT LOCATOR 8 THEORY OF OPERATION 8 ...
Page 478: ...9 12 C60 Breaker Protection System GE Multilin 9 6 DISPOSAL 9 MAINTENANCE 9 ...
Page 492: ...A 14 C60 Breaker Protection System GE Multilin A 1 PARAMETER LISTS APPENDIX A A ...
Page 648: ...E 10 C60 Breaker Protection System GE Multilin E 1 OVERVIEW APPENDIX E E ...
Page 660: ...F 12 C60 Breaker Protection System GE Multilin F 2 DNP POINT LISTS APPENDIX F F ...
Page 670: ...H 8 C60 Breaker Protection System GE Multilin H 2 ABBREVIATIONS APPENDIX H H Z Impedance Zone ...
Page 672: ...H 10 C60 Breaker Protection System GE Multilin H 3 WARRANTY APPENDIX H H ...
Page 682: ...x C60 Breaker Protection System GE Multilin INDEX ...