Chapter 4 - Room Planning

Page 51  

4 – Room Pla

nning

Chapter 4

Room Planning

Section 1.0

Required Systems Clearances

Consult your local GE Sales and Service Representative about your specific needs.

Some possible room size dimensions are shown in the tables below. 

Limited Access Rooms (width only):

Minimum Width: 3353 mm (11ft. );  356 mm  (14in. ) cover to wall
Average Width: 3708 mm (12ft. 2in. );  711 mm (28in.) cover to wall

Short Footprint (length only):

Minimum length: 5480 mm (18ft. ) 

Additional component dimensions are available in 

Figure 4-7

 through 

Figure 4-15

 of this document. 

Consult your local General Electric Project Manager of Installation for your appropriate room 
specifications.
For equipment clearance requirements, refer to 

Section 2.0

Remember, sufficient Regulatory and 

Service clearances must be maintained around equipment for full operation, service and safety.
Cable length is an important consideration in room layout. A set of short cables (B71172CA) and a 
set of long cables (B71182CA) are optional for BrightSpeed system. 
Note, also, that where possible, the cables should enter the gantry from the rear, utilizing the rear 
cable cover assembly. Alternate cable entry is possible at the center of the gantry (refer to the 
Installation template). 

Excess cable length cannot be stored behind the console or PDU. 

Long cable must not be cut or shortened. 

Excess cable may be stored in conduits, a cable storage box if present, or the floor duct, 
provided sufficient space is available. Observe the fill rate for each option. If there are 
questions regarding local electrical or building codes, consult the project electrical contractor 
or electrician.

All NEC 70-E Electrical Regulations regarding conduit or duct fill must be observed.

Recommended Scan Room 
Size

Typical Scan Room Size

Clearance 
Requirements

3962 x 6299 mm 
(13ft.  x 20ft. 8in. )

3912 x 5868 mm 
(12ft. 10in. x 19ft. 3in.)

see 

Figure 4-1

Table 4-1 List of Scan Room Layouts

Recommended Ctrl Room Size 
(Standard Console Table)

Recommended Ctrl Room 
Size (Freedom Workspace 
Console Table)

3962 x 2743 mm 
(13ft.  x 9ft. )

3861 x 2500 mm 
(12ft. 8in.  x 8ft. 2in. )

Table 4-2 List of Control Room Layouts

Summary of Contents for BrightSpeed Elite

Page 1: ...5141177 100 Rev 14 2006 2015 General Electric Company All Right Reserved GE Healthcare OPERATING DOCUMENTATION BrightSpeed Elite Edge Excel Pre Installation Manual...

Page 2: ...41177 100 REVISION 14 BRIGHTSPEED ELITE EDGE EXCEL PRE INSTALLATION Page 2 Effectivity The information in this manual applies to the following BrightSpeed Series CT Systems BrightSpeed Elite BrightSpe...

Page 3: ...u nik Zanemarite li ovo upozorenje mo e do i do ozljede davatelja usluge operatera ili pacijenta uslijed strujnog udara mehani kih ili drugih rizika V STRAHA CS Tento provozn n vod existuje pouze v an...

Page 4: ...ing may result in injury to the service provider operator or patient from electric shock mechanical or other hazards HOIATUS ET See teenindusjuhend on saadaval ainult inglise keeles Kui klienditeenind...

Page 5: ...telmezt k Ezen figyelmeztet s figyelmen k v l hagy sa a szolg ltat m k dtet vagy a beteg ram t s mechanikai vagy egy b vesz lyhelyzet miatti s r l s t eredm nyezheti A V RUN IS essi j nustuhandb k er...

Page 6: ...or et annet spr k er det kundens ansvar s rge for oversettelse Ikke fors k reparere utstyret uten at denne serviceh ndboken er lest og forst tt Manglende hensyn til denne advarselen kan f re til at se...

Page 7: ...sult rii i n elegerii acestui manual de service Ignorarea acestui avertisment ar putea duce la r nirea depanatorului operatorului sau pacientului n urma pericolelor de electrocutare mecanice sau de al...

Page 8: ...rvice p utrustningen om du inte har l st och f rst r den h r servicehandboken Om du inte tar h nsyn till den h r varningen kan det resultera i skador p serviceteknikern operat ren eller patienten till...

Page 9: ...engineers All of GE s electrical work on these products will comply with the requirements of the applicable electrical codes The purchaser of GE equipment shall only utilize qualified personnel i e GE...

Page 10: ...used batteries according to the manufacturer s instructions ATTENTION Danger d Explosion Il y a danger d explosion s il y a replacement incorrect de la batterie Remplacer uniquement avec une batterie...

Page 11: ...ponent Noise Levels Updated the cooling requirement table in Section 2 0 Updated Figure 5 1 Sample Room Layout showing approximate EMI requirements in Section 4 0 Chapter 6 updated floor loading speci...

Page 12: ...s updated content for Damage In Transportation Chapter 4 updated gantry width Section 2 1 2 updated Regulated Minimum Working Clearance by Major Subsystem Section 6 4 updated for FWS Seismic informati...

Page 13: ...nts 4 6 27 06 Chapter 3 Updated Table 3 1 BrightSpeed System Options Chapter 4 Updated recommended room layout and minimun room layout Updated Section 8 4 Floor Levelness Chapter 6 Updated seismic mou...

Page 14: ...GE HEALTHCARE DIRECTION 5141177 100 REVISION 14 BRIGHTSPEED ELITE EDGE EXCEL PRE INSTALLATION Page 14 Revision History...

Page 15: ...h HPower Table 71 Figure 4 8 Gantry shown tilted 30 top and 30 bottom for BSD Elite Edge Excel with HPower Table 72 Figure 4 9 Table and Gantry Side View for BSD Elite with GT1700 Table 73 Figure 4 10...

Page 16: ...666 3 111 Figure 6 8 GOC4 LCGOC AIO Operator Console 112 Figure 6 9 TIO and NIO16 Console Seismic Mounting Hole Position 113 Figure 7 1 Gantry with dollies 119 Figure 7 2 Console packing 121 Figure 7...

Page 17: ...terconnect Box for Europe 1 2 156 Figure 9 13 Power Distribution Interconnect Box for Europe 2 2 157 Figure A 1 Standard Service Access 161 Figure A 2 Front Cover Removal and Storage to Left Side 162...

Page 18: ...GE HEALTHCARE DIRECTION 5141177 100 REVISION 14 BRIGHTSPEED ELITE EDGE EXCEL PRE INSTALLATION Page 18 Table of Figures...

Page 19: ...aration con t 39 Table 1 10 Separation Distances 40 Table 3 1 BrightSpeed System Options 47 Table 4 1 List of Scan Room Layouts 51 Table 4 2 List of Control Room Layouts 51 Table 4 3 Console Subsystem...

Page 20: ...care Supplied Cables for NIO16 Console Standard Run 2281840 14 UL Information 136 Table 9 5 Extended Cables 137 Table 9 6 TIO Console Extended Cables 137 Table 9 7 GE Healthcare Supplied NIO16 Console...

Page 21: ...trical Equipment for EMC 37 4 1 General Scope 37 4 2 Electromagnetic Emission 37 4 3 Electromagnetic Immunity 38 4 3 1 Limitations Management 40 4 4 Use Limitation 40 4 4 1 External components 40 4 5...

Page 22: ...egulated Minimum Working Clearance by Major Subsystem 53 2 1 3 Terms and Definitions 57 2 2 Additional Regulatory Clearance Information 58 2 2 1 Minimum Room Size Limited Access 58 2 2 1 1 Regulatory...

Page 23: ...edom Workspace Table 79 Section 7 0 Minimum Dimensions and Clearances 83 7 1 Options 83 7 2 System Operation 83 7 3 Injector Control 83 Section 8 0 Structural Requirements 84 8 1 Table and Gantry Moun...

Page 24: ...01 4 7 UPS 101 4 8 Equipment EMI Envelopes 102 Section 5 0 System Component Noise Levels 102 Chapter 6 Floor Loading and Weights 103 Section 1 0 Floor Loading 103 Section 2 0 Mounting Data Including S...

Page 25: ...8 1 Short Term Storage Less than 6 months 122 8 2 Construction Site Storage 122 8 3 Long Term Storage 6 months or more 122 Section 9 0 Extreme Temperature Transportation and Deliveries 123 Section 10...

Page 26: ...lied Freedom Workspace Table Extended Cables Kit 137 3 3 GEMS Supplied Optional Long Run 143 3 4 GEMS Supplied Cables of Options 146 3 5 Contractor Customer Supplied 148 Section 4 0 Contractor Supplie...

Page 27: ...ss specifically mentioned GE Healthcare does not provide or install wires conduits junction boxes and ducts as illustrated in this publication All CT site plans preliminary concepts and final working...

Page 28: ...s installed and no remaining ceiling work is required Final floors covering installed with no remaining dust causing floor work required All room millwork installed as shown on the site print All plum...

Page 29: ...ness and thickness Review HVAC requirements including system regulation and patient comfort Review operational clearances to see if your daily used items fit such as beds and carts Emergency medical e...

Page 30: ...cluding floor thickness meet all of the above requirements Existing HVAC capacity and regulation meet all of the above requirements Existing CT suite meets all of the above regulatory and minimum size...

Page 31: ...ation Determine delivery route into the scan room Determine if tilt dollies or riggers are required Determine if elevators doorways and hallways are adequate for delivery Determine if floor protection...

Page 32: ...__________________________ AW Direct Connect address ____________________________________________________________ Do you want HIPAA enabled No___ Yes ___ Do you want automatic downloads enabled No___...

Page 33: ...met Name __________________________________________________ Have the specific site requirements been discussed with the contractor Refer to the GE final drawings specifications See Table 1 3 below Has...

Page 34: ...__ Mandatory Is the network installed are network jacks installed and is the entire network tested Mandatory Broadband VPN installed setup Mandatory Are network software options ordered ____ HIS RIS o...

Page 35: ...toduction Will acceptance performance testing or bio medical testing be required No__ Yes __ Date ___________ Are trash and or recycling bins available for the removal of papers boxes etc during the i...

Page 36: ...ery Route Floor Protection Purchaser Trash disposal Contractors onsite Vendors onsite Options onsite Responsibility GE Complete GE checklist Send copy to vendor Review Options Review Cables Purchaser...

Page 37: ...ngths referenced in the MIS MAPS or system cable interconnect diagrams 4 2 Electromagnetic Emission Table 1 7 Emission Declaration EMC Emissions Guidance Declaration for BrightSpeed System The BrightS...

Page 38: ...input output lines 2 kV for power supply lines 1 kV for input output lines Mains power quality should be that of typical commercial or hospital environment Surge IEC 61000 4 5 1 kV line line 2 kV line...

Page 39: ...n watts W according to the transmitter manufacturer and d is the recommended separation distance in metres m Field strengths from fixed RF transmitters as determined by an electromagnetic site surveya...

Page 40: ...tromagnetic environment in which radiated RF disturbances are controlled The customer or the user of the BrightSpeed System can help prevent electromagnetic interference by maintaining a minimum dista...

Page 41: ...ents accessories subsystems systems which are electrically connected to the BrightSpeed System must have all AC power supplied by the same power distribution panel line 4 5 4 Stacked Components Equipm...

Page 42: ...GE HEALTHCARE DIRECTION 5141177 100 REVISION 14 BRIGHTSPEED ELITE EDGE EXCEL PRE INSTALLATION Page 42 Chapter 1 Introduction...

Page 43: ...d in the same room as the scanner due to the possibility of chemical contamination of BrightSpeed Series components Such chemicals can contribute to increased equipment failures increased system downt...

Page 44: ...ice clearances shown on the print are observed Using the template P N 5160024 5341997 shipped with the system locate the anchor holes Make sure they clear structural interferences in the floor Clean t...

Page 45: ...ter 2 Pre Installation Overview Page 45 2 Overview Figure 2 1 Hole Locations GANTRY Base TABLE 4 Level or 1M Bubble Level Right Left Back Leveling Pad and Anchor Location 2 Leveling Pad and Anchor Loc...

Page 46: ...GE HEALTHCARE DIRECTION 5141177 100 REVISION 14 BRIGHTSPEED ELITE EDGE EXCEL PRE INSTALLATION Page 46 Chapter 2 Pre Installation Overview...

Page 47: ...it Freedom WorkSpace B78442CA Freedom Workspace Standard B78452CA Freedom Workspace kit Wide B7866AB SmartScore Option EKG Monitor and Recording Device B7900WB SmartScore 4 0 Package B7500PL ConnectPr...

Page 48: ...E EDGE EXCEL PRE INSTALLATION Page 48 Section 1 0 Option Catalog Numbers B75212BS B78892AC ASIR Upgrade Note The catalog number with is only for BrightSpeed Elite System with TIO NIO16 console CATALOG...

Page 49: ...r System 2 1 Application The CT scanner system includes hardware and software to support patient data acquisition and image analysis for whole body computed tomography 2 2 Configuration The base scann...

Page 50: ...GE HEALTHCARE DIRECTION 5141177 100 REVISION 14 BRIGHTSPEED ELITE EDGE EXCEL PRE INSTALLATION Page 50 Section 2 0 Base Scanner System Figure 3 2 BrightSpeed Elite Base Scanner System with GT1700 Table...

Page 51: ...out A set of short cables B71172CA and a set of long cables B71182CA are optional for BrightSpeed system Note also that where possible the cables should enter the gantry from the rear utilizing the re...

Page 52: ...requirements must be met Figure 4 1 Regulatory Clearance Requirements for BrightSpeed System Configurations Note See Section 3 0 for Service Clearances 914 to 1219mm 36 to 48 in 914 to 1219mm 36 to 48...

Page 53: ...the following circumstances If the wall or surface directly facing the electrical equipment is grounded e g brick concrete or tile or includes grounded protrusions such as medical gas ports metal door...

Page 54: ...If the opposite wall is grounded and exposed live parts of 151 600 volts are present 1067 mm 42 in is required Service Access Width Left Right of workspace 762 mm 30 in This is the width of the workin...

Page 55: ...pment whichever is greater is required Direction of Service Access Table Sides 914 mm 36 in This distance can be reduced to 711 mm 28 in provided a written and signed approval is obtained by the local...

Page 56: ...the ceiling or overhead obstruction s A minimum of 1981 mm 78 in or the height of the equipment whichever is greater is required Table 4 7 UPS Subsystem Work Space Requirement Minimum Clear Space Add...

Page 57: ...minimum of 762 mm 30 in or the width of the equipment whichever is greater Head Clearance The height dimension of the workspace The height of the workspace measured from the floor at the front edge o...

Page 58: ...ice procedure One Service Engineer shall be able to accomplish all service component replace tasks listed without the need for special tools or equipment such as a tube change detector change and HV t...

Page 59: ...lations Typical Room Size 3912 x 5868 mm 12ft 10in x 19ft 3in Same Regulatory requirements apply 2 2 2 3 Minimum Room Size This room size and configuration is the smallest functionally acceptable spac...

Page 60: ...ion 2 0 Regulatory Clearances 2 2 3 How to Measure How to measure From the farthest outward component No obstruction areas Gantry Side vertical covers outward Front or back vertical covers outward Not...

Page 61: ...m 28 in but greater than 256 mm 14 in measured from the covers to the left sidewall In this configuration service egress and workspace are compromised around the gantry 3310 mm 10ft 10 in to 3665 12 f...

Page 62: ...0 Regulatory Clearances Room B Less than 36 in but greater than 28 in measured from the covers to the left sidewall In this configuration service egress and workspace are acceptable around the gantry...

Page 63: ...5 Recommended Room Size Requirement Layouts Note Your room layout may meet the Recommended or Typical room requirements but look different than the room shown below Contact your sales person to have...

Page 64: ...Compliance Workspace Clearance Perpendicular to Equipment Regulatory Compliance Minimum Service Clearance Reference Clearance definitions On the following pages Note 1 Mandatory clear space envelope d...

Page 65: ...ear or either side of the gantry If gantry service requires both the front and rear covers be removed then these covers must be positioned within the room in such a manner as to not violate the regula...

Page 66: ...console be maintained at all times for service activity Additionally sufficient space needs to be provided for repositioning of the console and side clearance for rear service access Egress as well a...

Page 67: ...of using Short Footprint function NOTICE Cradle limitation must comply with country or local regulatory clearance requirements Cradle movement limitation set for short footprint must be approved by cu...

Page 68: ...57mm Shown in Figure 4 5 D Gantry left side to wall no less than 356mm 14 in Refer to Section 3 0 for details about Limited Access E Gantry right side to wall no less than 914 mm 36 in If Short Footpr...

Page 69: ...or details The control room must provide a suitable operating environment for the console electronic and operator working comfort The console cannot be dismantled of have components removed or rearran...

Page 70: ...easy service access A storage Cabinet is provided as option B77292CA 5 3 Advantage Workstation AW Refer to Advantage Workstation Pre Installation Manual and Installation Service Manual ITEM SIZE WEIGH...

Page 71: ...e and Gantry Figure 4 7 Table and Gantry Side View for BSD Elite Edge Excel with HPower Table DESCRIPTION WIDTH DEPTH HEIGHT INCH MM INCH MM INCH MM Color printer 23 584 18 457 7 178 Remote Color Moni...

Page 72: ...SPEED ELITE EDGE EXCEL PRE INSTALLATION Page 72 Section 6 0 Component Dimensions Figure 4 8 Gantry shown tilted 30 top and 30 bottom for BSD Elite Edge Excel with HPower Table AIR OUT AIR IN 2074 81 7...

Page 73: ...4 9 Table and Gantry Side View for BSD Elite with GT1700 Table 991 3ft 3in CRADLE CENTER ISO CENTER SCAN PLANE 1016 3ft 4in 1036 3ft 4 3 4in 2749 9ft 1 4in 1944 6ft 4 1 2in 1094 3ft 7 1 8in AIR OUT A...

Page 74: ...imensions Figure 4 10 Gantry shown tilted 30 top and 30 bottom for BSD Elite with GT1700 Table 1016 3ft 4in 991 3ft 3in CRADLE CENTER 3 0 ISO CENTER SCAN PLANE 2075 6ft 9 3 4in 3595 11ft 9 1 2in AIR I...

Page 75: ...it NGPDU Power Distribution Unit NGPDU NOTE DIMENSIONS ARE IN INCHES MILLIMETERS REAR VENT AREA 41 8 1062 REAR VIEW TOP VIEW REAR AC POWER INPUT BOX AC POWER INPUT BOX 2 6 67 I O CONNECTIONS PANEL FRO...

Page 76: ...GHTSPEED ELITE EDGE EXCEL PRE INSTALLATION Page 76 Section 6 0 Component Dimensions 6 3 Operator s Console Figure 4 12 Operator s Console with Standard Table 705 DIM MIN MAX A 680 883 B 680 807 C 1020...

Page 77: ...g Page 77 4 Room Planning Figure 4 13 TIO Operator s Console WALL 100 Min 3 7 8in CLEARANCE 740 2ft 5 1 8in 510 1ft 1 1 8in AIR OUT AIR IN 301 11 7 8in 640 2ft 1 1 4in 640 2ft 1 1 4in 301 11 7 8in 262...

Page 78: ...s Console SIDE VIEW SIDE VIEW FRON FRONT VIEW VIEW TOP VIEW VIEW BOT BOTTOM VIEW OM VIEW 546 21 5 546 21 5 470 18 5 470 18 5 656 25 8 656 25 8 832 1 32 8 832 1 32 8 WALL 96 3 8 96 3 8 740 29 150 3 150...

Page 79: ...m Workspace Table Height of Freedom Workspace is adjustable Figure 4 15 Freedom Workspace Table part 5160735 Height Seismic Bracket Supplied with FWS Attach seismic brackets to the gap above the adjus...

Page 80: ...EVISION 14 BRIGHTSPEED ELITE EDGE EXCEL PRE INSTALLATION Page 80 Section 6 0 Component Dimensions Figure 4 16 Freedom Workspace Table part 5168666 683 26 9 912 36 0 567 22 3 718 28 3 366 14 4 916 36 1...

Page 81: ...L PRE INSTALLATION Chapter 4 Room Planning Page 81 4 Room Planning Figure 4 17 Freedom Workspace Table Wide part 5168666 2 683 912 2ft 2 7 8in 2ft 11 7 8in 576 738 1ft 10 5 8in 2ft 5in 379 1ft 2 7 8in...

Page 82: ...RE INSTALLATION Page 82 Section 6 0 Component Dimensions Figure 4 18 Freedom Workspace Table Standard Narrow part 5168666 3 683 912 2ft 2 7 8in 2ft 11 7 8in 577 722 1ft 10 3 4in 2ft 4 3 8in 373 1ft 2...

Page 83: ...figurations and lengths Refer to Injector documentation for detailed installation instructions SYSTEM OPERATION MM INCHES Finished ceiling to floor recommended 2743 0mm 108 0 in Finished ceiling to fl...

Page 84: ...ied weight of table and gantry and the individual contact area loading of these components Refer to Section 6 0 for each of the three 3 major components of the BrightSpeed system Support areas of the...

Page 85: ...Minimum gantry height at this specification will be 1 2 15 mm to prevent cable crushing Table level may not be achievable if overall floor levelness is greater than the specification Overall floor lev...

Page 86: ...ation of the window is dependent on the position of Operator Workspace position Consult Section 10 0 of this chapter and a qualified radiological health physicist for radiation protection requirements...

Page 87: ...provided by the customer and it is used to connect the console to a wall box See Notes on Figure 9 5 Some customer site units may require cable duct work or conduit to route connecting network cables...

Page 88: ...20 TIO Console and Host Computer Rear To Advantage Workstation if Hispeed connection is required HOST COMPUTER REAR PANEL ETHERNET PORTS A SWITCH HUB B HOSPITAL C GANTRY D BACKUP USB PORTS 1 TRACKBALL...

Page 89: ...ponsibilities Provide GE Healthcare Installation Project Manager with an accurate site address telephone number contact name and e mail address for the Customer Champion Coordinate VPN activities betw...

Page 90: ...rmine site readiness for broad band Contact your Installation Project Manager for the name of the zone Broad Band Specialist Work with the Customer Champion to complete any identified infrastructure c...

Page 91: ...CTDI phantom body and a 20 cm water phantom head with the technique shown The mAs kV and aperture scaling factors shown in Table 4 11 can be used to adjust exposure levels to the scan technique used...

Page 92: ...re 4 22 Typical Scatter Survey Head Filter 0 33 0 33 0 65 0 65 1 3 1 3 2 6 2 6 0 33 0 33 0 65 0 65 1 3 1 3 2 6 2 6 HEAD PHANTOM Technique 140 kV 100mA 1 Sec 4 x 5 00mm Technique 140 kV 100mA 1 Sec 4 x...

Page 93: ...4 23 Typical Scatter Survey Body Filter 0 65 0 65 1 3 1 3 2 6 2 6 5 2 5 2 Technique 140 kV 100mA 1 Sec 4 x 5 00mm 50cm 50cm BODY SCATTER PHANTOM 0 65 0 65 1 3 1 3 2 6 2 6 5 2 5 2 Technique 140 kV 100...

Page 94: ...ALTHCARE DIRECTION 5141177 100 REVISION 14 BRIGHTSPEED ELITE EDGE EXCEL PRE INSTALLATION Page 94 Section 10 0 Radiation Protection Figure 4 24 Fluoro Stand Position Figure 4 25 Scatter Plot of Fluoro...

Page 95: ...GE HEALTHCARE DIRECTION 5141177 100 REVISION 14 BRIGHTSPEED ELITE EDGE EXCEL PRE INSTALLATION Chapter 4 Room Planning Page 95 4 Room Planning Figure 4 26 Scatter Plot of Fluoro Head...

Page 96: ...ON Page 96 Section 11 0 Patient Environment Section 11 0 Patient Environment The patient environment is defined as the following picture Only Scanning Gantry Patient Table components and the following...

Page 97: ...ive to the presence of sulfide chloride and nitrate contaminates Sulfur is the most damaging If high levels of contaminates exist site may want to consider appropriate air filtration systems Section 1...

Page 98: ...be installed Note readings before and after installation to verify the true temperature and humidity in your environment Consider heating ventilating air conditioning HVAC needs and redundancy An air...

Page 99: ...om 492 ft to 9842 5 ft 150 meters to 3000 meters SYSTEM COMPONENT BTU HR WATT 1 Gantry recommended See NOTE 1 18 766 5 500 2 HPower Table GT1700 Table 682 1023 200 300 3 Power distribution unit 5 118...

Page 100: ...RBANCES FROM 30 MHz TO 1 GHz The Warning statement above is specified by IEC 60601 1 2 First Edition 1993 4 2 Color Monitor Locate color monitors in ambient static magnetic fields of less than 5 x 10...

Page 101: ...gnetic field of a three phase transformer is much less than that of a bank of three single phase transformers of equivalent power rating Large electric motors are a source of substantial EMI High powe...

Page 102: ...gantry during a CT scan acquisition It is less than 75 dBA when measured at a distance of one meter from the nearest gantry surface in any direction Patient Table Gantry Power Distribution Unit Opera...

Page 103: ...87 175 852 Rectangular base 17 X 57 5 432 X 1460 with five round pads each 2 5 63 5 in contact with floor Worst case cantilever pull on any bolt is 1235 lb 561 kg Hilti Kwik Bolt II 1 2in 12 7mm diame...

Page 104: ...19 190 48 8 x 48 6 1240 x 1235 138 666 True In One Console w o monitors 192 87 18 5 X 29 2 470 x 740 99 483 NIO16 Console 176 80 19X29 470X740 Four Casters support Monitor LCD each 20 9 16 5 x 9 7 420...

Page 105: ...the closest adjacent hole the second anchor shall be installed to the standard depth and torque specifications Note If the Installers cannot set all for anchors for the GT1700V table the installer mu...

Page 106: ...GE HEALTHCARE DIRECTION 5141177 100 REVISION 14 BRIGHTSPEED ELITE EDGE EXCEL PRE INSTALLATION Page 106 Section 2 0 Mounting Data Including Seismic Figure 6 1 Typical Floor Anchor Gantry and Table...

Page 107: ...R Anchor Anchor Anchor Anchor Left Back Front Anchor Location 2 Anchor Location 1 Anchor Location 4 Anchor Location 3 Note Adjusters are used at each anchor location Anchor hole ID is 1 2 5 cm Void be...

Page 108: ...ismic Figure 6 4 Patient Table H Power CT3511A 16 00 406 4 CRADLE EXTEN SION 198 96 5053 6 91 90 2334 3 Z NOTE DIMENSIONS ARE IN INCHES MILLIMETERS CENTER OF GRAVITY CENTER OF GRAVITY IS WITH 450 LB 2...

Page 109: ...s Page 109 6 Floor Loading Figure 6 5 Patient Table GT1700 Note See Figure 4 7 for cradle operational limits 378 1ft 2 7 8in 854 2ft 9 5 8in 2242 7ft 4 1 4in 1979 6ft 5 7 8in 844 2ft 9 1 4in 400 CRADL...

Page 110: ...NGPDU SERVICE AREA MINIMUM AIR FLOW CLEARANCE NOTES DIMENSIONS ARE IN INCHES MILLIMETERS INDICATES CENTER OF GRAVITY Current PDU Seismic Bracket has holes alreadly drilled Drill holes on the floor ac...

Page 111: ...GE HEALTHCARE DIRECTION 5141177 100 REVISION 14 BRIGHTSPEED ELITE EDGE EXCEL PRE INSTALLATION Chapter 6 Floor Loading and Weights Page 111 6 Floor Loading Figure 6 7 FWS Assembly 5168666 3...

Page 112: ...GE HEALTHCARE DIRECTION 5141177 100 REVISION 14 BRIGHTSPEED ELITE EDGE EXCEL PRE INSTALLATION Page 112 Section 2 0 Mounting Data Including Seismic Figure 6 8 GOC4 LCGOC AIO Operator Console 705...

Page 113: ...CARE DIRECTION 5141177 100 REVISION 14 BRIGHTSPEED ELITE EDGE EXCEL PRE INSTALLATION Chapter 6 Floor Loading and Weights Page 113 6 Floor Loading Figure 6 9 TIO and NIO16 Console Seismic Mounting Hole...

Page 114: ...GE HEALTHCARE DIRECTION 5141177 100 REVISION 14 BRIGHTSPEED ELITE EDGE EXCEL PRE INSTALLATION Page 114 Section 2 0 Mounting Data Including Seismic...

Page 115: ...n Loading Dock Deliveries Facilities without a loading dock require a Lift Gate or Tilt Bed truck Such deliveries require unloading the system components from the truck bed to ground level and then tr...

Page 116: ...E SEVERE PERSONAL INJURY OR DEATH THE DOLLIES ARE NOT DESIGNED TO BE USED AS AN ATTACHMENT POINT FOR ANY METHOD OF LIFTING THE SUBSYSTEMS ATTACHING LIFTING STRAPS CABLES OR MECHANISMS TO THE DOLLY HAN...

Page 117: ...rizontal fixtures must appear on the order for them to ship with the system If delivery requires vertical lifting the PMI adds the appropriate identifier to the order The gantry ships in a vertical li...

Page 118: ...arance dollies go to http www umi dollyshop com 3 3 Tilting Table Dollies Deliveries involving small elevators with a depth of at least 2438 mm 96 in require tilting table dollies If storing the syste...

Page 119: ...evator manufacturer if gantry weight exceeds elevator capacity Minimum hallway and door size for gantry with covers and dollies attached but side rails removed is 101 6 cm 40 in For alternative liftin...

Page 120: ...ithout side covers installed Covers are shipped in separate boxes The table is mounted with two dollies For the table dimensions with dollies refer to Table 7 3 Section 6 0 Console Considerations LCGO...

Page 121: ...ons of the console alone as shipped are 740mm 29 in deep 470mm 19 in wide and 640mm 25 in high NIO16 Console The console is shipped without covers installed The covers are delivered in the Product Gra...

Page 122: ...above 8 2 Construction Site Storage When storing the CT system at a construction site be sure to adhere to the following storage requirements Do not damage or puncture the shipping crate Do not remove...

Page 123: ...res should be avoided during system transportation and delivery Extreme temperatures consist of temperatures below 18 C 0 F or above 49 C 120 F without humidity control When transporting the CT system...

Page 124: ...me and decreased reliability Film processor equipment installation must meet the manufacturer s requirements e g ventilation specifications and all applicable national and local codes Also considerati...

Page 125: ...age resulting from shock or vibration e g monitor CD ROM hard drive or console failure may not become evident until after the system is installed 11 2 3 Avoid Tipping All system components must remain...

Page 126: ...GE HEALTHCARE DIRECTION 5141177 100 REVISION 14 BRIGHTSPEED ELITE EDGE EXCEL PRE INSTALLATION Page 126 Section 11 0 Handling Requirements...

Page 127: ...ower wiring between the facility main distribution panel and the PDU should be kept as short as possible When routing the power wiring all three phase wires and ground must be run in the same conduit...

Page 128: ...slice 75 kVA is standard rating 90kVA is an optional rating The BrightSpeed system operates on three phase power meeting the following specifications Note The value in the brackets is for 75kVA Volta...

Page 129: ...ransients Sags and surges of the power line must not exceed the absolute range limits shown in Table 8 1 Maximum transient voltages should be limited to 1500V peak 2 6 Grounding Metal conduit raceway...

Page 130: ...size is 112 5 kVA rated 2 4 regulation at unity power factor For this configuration the minimum recommended feeder size and overcurrent protection device based on line voltage is shown in Table 8 2 Mi...

Page 131: ...WG OR MCM SQ MM VAC 200 VAC 220 VAC 240 VAC 380 VAC 400 VAC 420 VAC 440 VAC 460 VAC 480 VAC 50 15 1 45 2 35 3 30 4 22 4 22 4 22 4 22 4 22 4 22 100 30 1 0 55 1 0 55 1 45 4 22 4 22 4 22 4 22 4 22 4 22 1...

Page 132: ...tal surfaces in the patient vicinity are grounded to the reference ground point For additional information refer to Electrical Safety Equipment Direction 46 014505 Figure 8 1 System Ground Map CONSOLE...

Page 133: ...appropriate Need for additional junction boxes is minimized by use of either a cable raceway system or a raised computer floor BrightSpeed Series systems use prefabricated cables with large plugs Ther...

Page 134: ...4 2 22 Dia 053 65 60 19 8 18 3 2343531 2 LVAC PDU to Console 2587 FT4 600 120VAC 90 12 3 483 3 10 56 4 2 22 Dia 054 n a LVAC Gantry to Table 1015 600 120VAC 3 14 055 28 20 8 5 5 97 2371450 2 Ground PD...

Page 135: ...600 208Y 120 90 13 8 542 5 8 56 4 2 22 Dia 053 65 60 19 8 18 3 2343531 2 LVAC PDU to Console 2587 FT4 600 120VAC 90 12 3 483 3 10 56 4 2 22 Dia 054 n a LVAC Gantry to Table 1015 600 120VAC 3 14 055 28...

Page 136: ...3528 2 LVAC PDU to Gantry 2587 FT4 600 208Y 120 90 13 8 542 5 8 56 4 2 22 Dia 053 65 60 19 8 18 3 2343531 2 LVAC PDU to Console 2587 FT4 600 120VAC 90 12 3 483 3 10 56 4 2 22 Dia 054 2343596 LVAC Gant...

Page 137: ...73 2 181 10 3 94 4600 100 USB Extension Cable 1 Trackball 5160574 118 11 3 94 3000 100 PS_2 Extension Cable 1 Keyboard 5160575 118 11 3 94 3000 100 PS_2 Extension Cable 1 Mouse 5160575 2 118 11 3 94 3...

Page 138: ...oard 1 3000 30 118 11 1 18 5332107 2 CABLE DVI to D SUB VIDEO CABLE Monitor 1 3000 20 118 11 0 79 5315370 CABLE USB TYPE A B PMT media Tower DVD RW USB external HDD 2 2000 78 74 5408703 DP to DVI cabl...

Page 139: ...eway Footswitches Power Pan System Ground Bus Vault Ground Front Bulkhead J11 TS1 TS2 A1J1 TGPU RUN 050 HVDC Power RUN 051 HVAC Axial Mtr Power Power Pan Bulkhead Footswitch Scan Display Console Monit...

Page 140: ...Bulkhead J11 TS1 TS2 A1J1 TGPU RUN 050 HVDC Power RUN 051 HVAC Axial Mtr Power Power Pan Bulkhead Footswitch Scan Display Console Monitors Power Cords Monitor Cables SCIM Trackball ICOM Keyboard RUN 0...

Page 141: ...Power Pan IPC System Ground Bus Vault Ground Bulkhead J11 TS1 TS2 A1J1 TGPU RUN 050 HVDC Power RUN 051 HVAC Axial Mtr Power Power Pan Bulkhead Footswitch Scan Display Console Monitors Power Cords 2142...

Page 142: ...dem AW Power Panel Ceiling Item 8 5116219 Item 10 2213219 Power Video Splitter Out Out In Item 2 2403438 3 Monitor Item 16 2403438 4 In room Monitor Signal IPC PANEL Injector Power Respiratory Monitor...

Page 143: ...8Y 120 90 13 8 542 5 8 56 4 2 22 Dia 053 80 75 24 5 22 86 2343531 LVAC PDU to Console 2587 FT4 600 120VAC 90 12 3 483 3 10 56 4 2 22 Dia 055 63 55 19 3 16 76 2371450 Ground PDU to Raceway 1284 VW 1 FT...

Page 144: ...a 052 63 57 19 3 16 76 2343528 LVAC PDU to Gantry 2587 FT4 600 208Y 120 90 13 8 542 5 8 56 4 2 22 Dia 053 80 75 24 5 22 86 2343531 LVAC PDU to Console 2587 FT4 600 120VAC 90 12 3 483 3 10 56 4 2 22 Di...

Page 145: ...254 90 15 3 604 4 14 11 2 44 Dia 052 63 58 19 3 17 56 2343528 LVAC PDU to Gantry 2587 FT4 600 208Y 120 90 13 8 542 5 8 56 4 2 22 Dia 053 80 75 24 5 22 86 2343531 LVAC PDU to Console 2587 FT4 600 120V...

Page 146: ...le To LCD 1015 VW 1 600 0V 105 1 8 15 4 6 2403438 4 HD 15 FEMALE TO HD 15 MALE 15 FEET 1Vp p 60 8 0 0 315 5 26 1 3 0 4 2355108 JUMPER CABLE FOR ADAPTING 2286150 TO WORK WITH H POWER MSUB 8 22 UPS 15 4...

Page 147: ...and Cables Adv 4D Resp 100 30 5 5199717 GANTRY TO RPM UNIT 2464 FT4 300 30VDC 80 6 6 0 26 4 22 37 1 45 Dia OPTION LENGTH ACTUAL USABLE UL CABLE INFORMATION UL Style Flam Rating Voltage Rating Voltage...

Page 148: ...URCE A1 Maximum Run Length 3 POWER 3 1 3 1 1 1 0 50 GROUND 3 1 3 1 RUN NO 2 FROM FACILITY DISCONNECT TO POWER MODULE A1 PM MAXIMUM RUN LENGTH 3 POWER 3 1 3 1 1 1 0 50 GROUND 3 1 3 1 1 NEUTRAL Not Requ...

Page 149: ...the system 5 10 OPTION KEY TO TELEPHONE SYSTEM see Note 1 NOTES 1 Used for remote diagnostics Option 2 Refer to the appropriate Pre installation Installation documents for the Laser Camera 3 Category...

Page 150: ...mponents Reference the system installation drawings supplied by Installation Support Services within your geographic area Refer to Table 9 16 on page 152 Table 9 13 Contractor Supplied Components ITEM...

Page 151: ...170021P10 2 Yes 006 000A 0250V 3AG FAST UL C REVIEWED TK 7 91 8 46 170021P101 1 Yes FUSE 20 AMPS 700 VOLTS 2 LONG X 9 16 DIA FAST BLOW 9 46 170021P106 1 Yes FUSE 8 AMPS 250 VOLTS BUSSMANN ONLY 10 46...

Page 152: ...A1 37 45 GE supplied Input cable 7 15 A1 SEO UPS 3 phase power source Output cable 7 15 35 max Legend Cable lengths are Usable Actual 37 45 PDU Customer supplied PDU Type Model Max Mom kVA Rating Rec...

Page 153: ...153 9 Interconnects Section 7 0 Typical Customer Supplied Wiring 7 1 Primary Power Disconnect Requires LOTO compatible disconnect to install this system If a UPS is required a GE Disconnect is strong...

Page 154: ...DIRECTION 5141177 100 REVISION 14 BRIGHTSPEED ELITE EDGE EXCEL PRE INSTALLATION Page 154 Section 7 0 Typical Customer Supplied Wiring Figure 9 8 Primary Power Disconnect A1 Fusible Disconnect and Magn...

Page 155: ...ical TS6 Warning Light Door Interlock Connections Figure 9 10 TS6 Room Door Interlock Connections With a Door Interlock Figure 9 11 TS6 Room Door Interlock Connections Without a Door Interlock 10 9 Do...

Page 156: ...14 BRIGHTSPEED ELITE EDGE EXCEL PRE INSTALLATION Page 156 Section 8 0 Recommended Power Distribution System For Europe Section 8 0 Recommended Power Distribution System For Europe Figure 9 12 Power D...

Page 157: ...LTHCARE DIRECTION 5141177 100 REVISION 14 BRIGHTSPEED ELITE EDGE EXCEL PRE INSTALLATION Chapter 9 Interconnection Data Page 157 9 Interconnects Figure 9 13 Power Distribution Interconnect Box for Euro...

Page 158: ...GE HEALTHCARE DIRECTION 5141177 100 REVISION 14 BRIGHTSPEED ELITE EDGE EXCEL PRE INSTALLATION Page 158 Section 8 0 Recommended Power Distribution System For Europe...

Page 159: ...n this appendix 1 2 Front Cover Removal Rather than storing the front cover straight forward from the gantry at the foot of the table the cover can be moved and stored on the right or left side of the...

Page 160: ...ps is prohibited 1 4 Condition References There are three possible minimum service space requirements based on the construction of the wall directly adjacent to the side of the gantry The following th...

Page 161: ...GE HEALTHCARE DIRECTION 5141177 100 REVISION 14 BRIGHTSPEED ELITE EDGE EXCEL PRE INSTALLATION Appendix A Alternate Cover Removal Options Page 161 A Covers Figure A 1 Standard Service Access...

Page 162: ...GE HEALTHCARE DIRECTION 5141177 100 REVISION 14 BRIGHTSPEED Page 162 Section 1 0 Alternate Cover Removal Options Figure A 2 Front Cover Removal and Storage to Left Side...

Page 163: ...LTHCARE DIRECTION 5141177 100 REVISION 14 BRIGHTSPEED ELITE EDGE EXCEL PRE INSTALLATION Appendix A Alternate Cover Removal Options Page 163 A Covers Figure A 3 Front Cover Removal and Storage to Right...

Page 164: ...GE HEALTHCARE DIRECTION 5141177 100 REVISION 14 BRIGHTSPEED Page 164 Section 1 0 Alternate Cover Removal Options Figure A 4 Front Cover Removal with Table Up Storage to Left Side...

Page 165: ...RE DIRECTION 5141177 100 REVISION 14 BRIGHTSPEED ELITE EDGE EXCEL PRE INSTALLATION Appendix A Alternate Cover Removal Options Page 165 A Covers Figure A 5 Front Cover Removal with Table Up Storage to...

Page 166: ...GE HEALTHCARE DIRECTION 5141177 100 REVISION 14 BRIGHTSPEED Page 166 Section 1 0 Alternate Cover Removal Options Figure A 6 Rear Cover Removal and Storage Straight Back...

Page 167: ...CARE DIRECTION 5141177 100 REVISION 14 BRIGHTSPEED ELITE EDGE EXCEL PRE INSTALLATION Appendix A Alternate Cover Removal Options Page 167 A Covers Figure A 7 Rear Cover Removal and Storage to Left or R...

Page 168: ...GE HEALTHCARE DIRECTION 5141177 100 REVISION 14 BRIGHTSPEED Page 168 Section 1 0 Alternate Cover Removal Options Figure A 8 Rear Cover Gantry Angled Storage in Corner...

Page 169: ...CT...

Page 170: ...170 www gehealthcare com...