OPM_MLE_LTE_350_1K0_1GB_V011
4
DE ML Series: user manual 1.1 (GB)
GE Digital Energy
™
ML Series
g
3.1 Start-up
3.1.1
Start-up, mains available
1 Press keypad 'ON' for 2 seconds
LED ‘LINE’ (already blinking) will illuminate continuously now.
2 The equipment connected to the UPS can now be switched on.
3.1.2
Start-up, mains not available (‘battery start’)
If the mains input is absent (power cord not connected, or mains failure):
1 Press keypad 'ON' for 2 seconds until LED ‘BAT’ illuminates.
The UPS operates on battery: it discharges the batteries.
3.2
Use: Normal Operation
3.2.1
Normal operation conditions:
•
the mains supply is present,
•
the UPS is on,
•
the load does not exceed the capacity of the UPS and
•
the operating temperature is below alarm level.
AVR (Automatic Voltage Regulation):
If the quality of the incoming mains is poor, the AVR boosts a low incoming voltage or reduces a
high one. The load receives a voltage within the normal range (see chapter 7).
3.2.2
Self test (UPS operation and battery condition)
In case of a system failure the output voltage can be lost. It is therefore recommended to switch
off the load before performing a self test. See chapter 6.
1 During normal operation, press keypad 'ON' for 2 seconds.
2 If the battery does not pass the self test, a ‘replace battery’ alarm is given. See 3.3.
3.2.3
Auto-off (no-load shutdown)
When mains is not available (mains failure or battery start) the UPS will switch off when the load
is less than 5% of the maximum load. In this way unnecessary discharging of the batteries is
avoided. The unit will automatically turn on again when mains power is restored. The no-load
shutdown function cannot be de-activated.
3.2.4 Switching
off
1 Press keypad ‘OFF’ for 2 seconds.
2 If electric isolation is required, unplug the power cord from the wall outlet.
3 - Operation