6
2.
W
IRING REQUIREMENTS
:
•
Single phase 240v a.c 10 A earth leakage protected supply.
•
Control input cables, Output signal cables (all to be shielded cable if over 8m runs).
•
Conduits preferably need to come up through base plate.
Plan view of installation and conduit entry location
3.
M
ECHANICAL
I
NSTALLATION
1.
Check that the gate runs smoothly throughout it’s travel and does not bind anywhere.
2.
IMPORTANT
Ensure gate stops are fitted at the fully open and closed positions
. These stops need to be
engineered and installed in such a way that they will be strong enough to stop the gate should the limits fail at
any time.
3.
Position the sliding gate operator on the concrete mounting pad and using a length of rack held onto the gate rail,
adjust the operator at a location where the pinion gear meshes fully onto the rack.
4.
Ensure the pinion wheel face is parallel with the gate rail and mark the holes through the mounting plate for
fixing.
5.
Dynabolt mounting plate to concrete pad using 12mm x 100mm dynabolts.
6.
Position gate operator so rack will fully mesh onto pinion gear.
7.
Loosen manual release knob on backside of gearbox (anticlockwise) and then start attaching rack to the gate
frame ensuring that the rack meshes onto the pinion gear with 1 – 2mm clearance.
8.
Rack is normally tek screwed to gate rail. After fixing the rack for the full length of the gate, run the gate back
and check the rack meshes to the pinion gear without being too high or too low.
Summary of Contents for GDS 240 PP
Page 10: ......