3.  Remove GPIO card from the server (if it exists). 

 

 

4.  Insert the additional gigabit network card into the same PCIe slot that was used by the PCI-e 

adaptor card. The tested gigabit network card model is 'INTEL Gigabit CT Desktop Adapter'. 

 

 

5.  Boot  up  the  server  and  apply  'upgrade-SX2000AR-9x-networkcard-20121109.tgz.enc'  on  7.8.X 

Server  SMS

Configuration

Assistance

USB.  This  upgrade  prompts  an  error  if  the  server 

eth0 or  eth1 has 192.168.1.x IP.  After  the upgrade  and reboot  on the server, eth2  appears on 
the server Control Panel and AdminPanel 

 Network as 192.168.1.13. 

Please  do not change 

this IP.

 

================================================================= 
Link URL:  

http://visitor:[email protected]/~service/9x/upgrade-SX2000AR-9x-networkcard-20121109.tgz.enc

 

 

User: visitor 
Password: wiije67 
 
md5sum: 2fc13509c8c172be25f24c73dd717e0e upgrade-SX2000AR-9x-networkcard-20121109.tgz.enc 
Upgrade password: 20121109 
================================================================= 

6.  Check that the HFR IMB is installed inside the projector properly and power up the projector and 

IMB. 

 

7.  Server eth1 is directly connected to IMB Ethernet 2. 

 

8.  Server eth0 is connected to projector Ethernet port (either directly or via a switch). 

 

Gigabit network card 

Summary of Contents for SX-2000ATO

Page 1: ...HFR UPGRADE MANUAL FOR SX 2000 A T TO SX 2000 A T R DIGITAL CINEMA SERVER WITH NEW INTEGRATED MEDIA BLOCK SMS version 9 0 December 19 2012...

Page 2: ...2 SX 2000 A T R Digital Cinema Server with New Integrated Media Block...

Page 3: ...ions 7 3 4 Notes 7 4 INSTALLING THE ADDITIONAL GIGABIT NETWORK CARD 8 5 UPGRADE PROCEDURE 10 5 1 Run the ServerID Upgrade 10 5 2 Apply Upgrade Package 1 10 6 APPLY UPGRADE PACKAGE 2 12 7 AFTER THE UPG...

Page 4: ...the separation between the equipment and receiver Connect the equipment into an outlet on a circuit different from that to which the receiver is connected Consult the dealer or an experienced radio TV...

Page 5: ...icensee regarding this Software and Manual This License Agreement replaces and supersedes all prior negotiations dealings and agreements between Licensor and Licensee regarding this Software and Manua...

Page 6: ...sfer between the server and HFR IMB Network cables with poor quality can cause video audio jitter during playback 1 2 Standard Upgrade Return List For SX 2000 upgrade the following items should be ret...

Page 7: ...1 X recommend it to be 192 168 0 X 3 SX 2000A T eth0 is connected to projector Ethernet either directly or via switch 4 SX 2000A T eth2 IP must NOT be 192 168 1 X eth2 is available after installing th...

Page 8: ...ure 1 Error message after replacement of the IMB 4 INSTALLING THE ADDITIONAL GIGABIT NETWORK CARD For TMS LMS data connection 1 Remove old IMB from the projector 2 Remove PCI e adaptor card from the s...

Page 9: ...de and reboot on the server eth2 appears on the server Control Panel and AdminPanel Network as 192 168 1 13 Please do not change this IP Link URL http visitor wiije67 ftp gdc tech com service 9x upgra...

Page 10: ...server for the DCI software upgrade and MUST run before running the main upgrade The following upgrade package must run based on your serial number A00000 A00999 upgrade serverID_A00xxx tgz enc A0100...

Page 11: ...sword and select the correct upgrade package Figure 4 Upgrade completed 3 The upgrade will take under one minute then a window Upgrade completed Click OK to reboot will pop up User should unplug the U...

Page 12: ...o playback a DCP from the server the upgrade may fail and the IMB LED will display a RED color after reboot When this happens only a GDC authorized personnel can recover the system Case 2 When convert...

Page 13: ...re 7 Server eth1 1 After the upgrade is completed powercycle both the server and projector with IMB 2 IMB marriage and service door clearance are recommended to be done on the server SMS Configuration...

Page 14: ...he SOM software upgrade package e g named as upgrade SOM step3 build56 20120911 tgz enc on SOM not server in the same way as Step 2 4 SOM not server AdminPanel Diagnostics Maintenance Software Upgrade...

Page 15: ...server 1 Click server SMS Shutdown Shutdown to turn off the server After the server is turned off the IMB SOM on projector will be down as well so the projector must be off 2 Power off the projector...

Page 16: ...ojector 1 TI IP 5 Configure Projector 1 TI IP on server SMS Configuration Cinecanvas Figure 10 SMS Interface 6 Once SM connected shows up on the server SMS the system is ready to playback both JPEG200...

Page 17: ...2 12 bit Figure 12 Activate PCF file 2 PCF should be MXFI_185 or MXFI_239 10 CAUTION 1 Please use Server SMS Shutdown Shutdown to turn off the server and IMB 2 After the server and IMB are turned off...

Page 18: ...18 11 APPENDIX 11 1 IMB Audio and GPIO Port Pin Layout Figure 13 IMB audio and GPIO port pin layout AES Audio GPIO...

Page 19: ...Ubi Crescent Ubi Tech Park Lobby B 06 25 Singapore 408564 Tel 65 6222 1082 China Shenzhen 5th Floor GDC Building No 9 Hi tech Middle 3 Road Science Technology Park Nanshan District Shenzhen P R China...