GCL System Integration Technology Co., Ltd.
Bring Green Power to Life
05
SAFETY & TRANSPORT
Unloading, Transportation and Storage
When the Modules are delivered to the project site, the freight car shall be ready in the
flat, even and open area for parking and unloading.
Forklift unloading: Choose the appropriate carrying forklift according to the commodity
weight, unload the Modules from the freight car and place them on flat ground.
Unloading with a crane: Affix the lifting belt in the wood supporting frame buckle (Fig. 1,
2). It is allowed only to lift one pallet at a time. Before lifting, it is necessary to confirm
whether the pallet and paper box are damaged and ensure that the lifting rope is robust
and firm. When being lifted close to the ground, the paper box will be gently placed in a
relatively flat position on the project site by two people, one on each side.
Figure 1 Wood Supporting Frame
Figure 2 Lifting Schematics
It is prohibited to stack the Modules in the project site.
During the transportation at the project site, the Modules shall not be stacked, but only
allowing for one layer in transportation.