INSTALLATION

1.

Mount the LS4 and install the supply cable. See picture 
1-4.
Phase-rotation is recommended in order to achieve even 
load on all phases when several LS4 stations are installed 
to same mains. For example:
1st LS4: L1, L2, L3
2nd LS4: L3, L1, L2
3rd LS4: L2, L3, L1
And so on…. 
Note: When DLM is pre-configurated from factory, follow 
the marked phase order label at incoming terminals. All 
pre-configured LS4 contains the information about this 
inside the cabinet
The gasket at the bottom of the LS4 need to tighten 
properly around the mains cable in order to avoid dirt, 
dust, bugs etc to enter the LS4. See picture 4.

2.

In cases with LS4 stations connected in a grid, install TP 
cable CAT6 with RJ45 connectors between each LS4 
station and the provided ethernet router/switch (located 
ie. in the LS4 master. Se example of ethernet wiring 
diagram picture 5, 6.
In cases with LS4 stations connected in a grid, installation 
of the LS4 stations need to follow the installation order in 
the attached Master/slave file. See picture 5, 6.

3.

In cases with external energy meter (for DLM function), 
connect the energy meter communication terminals A- and 
B+ to LS4 Master station terminals 200 A-) and 201 
(B+). The energy-meters modbus adress must be set to 
#2. The modbus RS-485 communication settings is: Baud 
9600, 8bit, 1 stop bit, no parity

4.

Turn on the electric power.

5.

Test the LS4 station on both sides with a EVSE-tester or an 
EV. In cases where authorization (by RFID tag or similar)  
is needed to start charging please contact the backend 
administrator.

6.

Fill in the warranty form completely.

Example of Master/Slave form for LS4 stations connected in a grid

Role

Serialnumber / M-number

Master

M00001

Slave 1

M00002

Slave 2

M00003

Slave 3

M00004

Slave 4

M00005

Slave 5
Slave 6
Slave 7
Slave 8
Slave 9
Slave 10

4

EN

Summary of Contents for LS4 Compact

Page 1: ...GARO LS4 LS4 Compact Installation Manual EN GARO AB Box 203 SE 335 25 Gnosj Phone 46 0 370 33 28 00 info garo se garo se Manual 380144 2 0 EN...

Page 2: ...eneral Information 3 INSTALLATION 4 NORMAL USE 5 Service Maintenance 5 LED Indications 5 Technical specifications 6 Service information 6 Form for annual service and maintenence 7 Warranty Conditions...

Page 3: ...ble is not allowed to be used Do not use private power generators as a power source for charging Incorrect installation and testing of the LS4 stations could potentially damage either the vehicles bat...

Page 4: ...master Se example of ethernet wiring diagram picture 5 6 In cases with LS4 stations connected in a grid installation of the LS4 stations need to follow the installation order in the attached Master sl...

Page 5: ...EV s instructions After charging Release the charging cable from your EV and place the charging cable at designated place SERVICE MAINTENANCE LED INDICATIONS 3pcs green Flash Waiting for authorization...

Page 6: ...ICE INFORMATION Care and maintenance GARO charging station LS4 The warranty will only remain valid if service is performed Service is performed once a year and must be documented General authorization...

Page 7: ...tion test by GARO test equipment or similar Check that electrical power is delivered by indications on test equipment Check RFID reader when available Indication by 2 or 3 flashes from LED s Check Typ...

Page 8: ...l and serial number 7 Warranty does not cover damage occurred by incorrect use of equipment use of any non original spare parts lack of maintenance or faults caused by disassembly of the product or un...

Page 9: ...FORM GARANTIFORMUL R LS4 Model M no Electrical installation data Group fuse A Supply cable dimension Function Test Testbox EV model Date Sign Installer Company Name Owner Customer Name Installation ad...

Page 10: ...CU AL picture 1 picture 2 10 EN...

Page 11: ...picture 3 picture 4 11 EN...

Page 12: ...with TP CAT6 cable to router switch 5pcs LS4 connected with TP CAT6 cable to router switch picture 5 picture 6 Example of DLM meter installation Modbus address 2 9600 8 1 no parity Terminals 200 A 201...

Page 13: ...Fuse Left Outlet FC2 Fuse Right Outlet QA1 Contactor Left Outlet QA2 Contactor Right Outlet XN1 N Neutral terminal XPE1 PE Terminal Protection Earth T1 Powersupply DC CC1 Charge Controller Master CC2...

Page 14: ...GARO AB Box 203 SE 335 25 Gnosj Phone 46 0 370 33 28 00 info garo se garo se EN...

Reviews: